Selection and Location of Fixed-Step Capacitor Banks in Distribution Grids for Minimization of Annual Operating Costs: A Two-Stage Approach

The problem regarding the optimal location and sizing of fixed-step capacitor banks in distribution networks with radial configuration is studied in this research by applying a two-stage optimization approach. The first stage consists of determining the nodes where the capacitor banks will be placed...

Full description

Autores:
Montoya, Oscar Danilo
Rivas-Trujillo, Edwin
Giral-Ramírez, Diego Armando
Tipo de recurso:
Fecha de publicación:
2022
Institución:
Universidad Tecnológica de Bolívar
Repositorio:
Repositorio Institucional UTB
Idioma:
eng
OAI Identifier:
oai:repositorio.utb.edu.co:20.500.12585/12181
Acceso en línea:
https://hdl.handle.net/20.500.12585/12181
Palabra clave:
Annual operating cost minimization
Daily load variations
Fixed-step capacitor banks
Successive approximation power flow method
Two-stage optimization approach
Rights
openAccess
License
http://creativecommons.org/licenses/by-nc-nd/4.0/
Description
Summary:The problem regarding the optimal location and sizing of fixed-step capacitor banks in distribution networks with radial configuration is studied in this research by applying a two-stage optimization approach. The first stage consists of determining the nodes where the capacitor banks will be placed. In this stage, the exact mixed-integer nonlinear programming (MINLP) model that represents the studied problem is transformed into a mixed-integer quadratic convex (MIQC) model. The solution of the MIQC model ensures that the global optimum is reached given the convexity of the solution space for each combination of nodes where the capacitor banks will be installed. With the solution of the MIQC, the suitable nodes for the installation of the fixed-step capacitors are fixed, and their sizes are recursively evaluated in a power flow methodology that allows for determining the optimal sizes. In the second stage, the successive approximation power flow method is applied to determine the optimal sizes assigned to these compensation devices. Numerical results in three test feeders with 33, 69, and 85 buses demonstrate the effectiveness of the proposed two-stage solution method for two operation scenarios: (i) operation of the distribution system under peak load conditions throughout the year, and (ii) operation considering daily demand variations and renewable generation penetration. Comparative results with the GAMS software confirm the excellent results reached using the proposed optimization approach. All the simulations were carried out in the MATLAB programming environment, version 2021b, as well as using the Gurobi solver in the convex programming tool known as CVX.