Effects of uncertainty on scheduling of highway construction projects
Time and cost overruns in highway construction are usual in Colombia. Contractors regularly fail in cost estimation and construction scheduling. An analysis of important factors on time and cost overruns in highway construction in southwest Colombia is presented in this paper. Forty highway construc...
- Autores:
-
Gómez, Hernán Darío
Orobio, Armando
- Tipo de recurso:
- Article of journal
- Fecha de publicación:
- 2015
- Institución:
- Universidad Nacional de Colombia
- Repositorio:
- Universidad Nacional de Colombia
- Idioma:
- spa
- OAI Identifier:
- oai:repositorio.unal.edu.co:unal/60657
- Acceso en línea:
- https://repositorio.unal.edu.co/handle/unal/60657
http://bdigital.unal.edu.co/58989/
- Palabra clave:
- 62 Ingeniería y operaciones afines / Engineering
Highway Infrastructure
construction scheduling
time overrun
cost overrun
- Rights
- openAccess
- License
- Atribución-NoComercial 4.0 Internacional
id |
UNACIONAL2_2c14d67503d38e1c1ddce8a84462ed8b |
---|---|
oai_identifier_str |
oai:repositorio.unal.edu.co:unal/60657 |
network_acronym_str |
UNACIONAL2 |
network_name_str |
Universidad Nacional de Colombia |
repository_id_str |
|
spelling |
Atribución-NoComercial 4.0 InternacionalDerechos reservados - Universidad Nacional de Colombiahttp://creativecommons.org/licenses/by-nc/4.0/info:eu-repo/semantics/openAccesshttp://purl.org/coar/access_right/c_abf2Gómez, Hernán Darío0a4e8dc5-0a44-4b1d-ad4f-8e64b072aded300Orobio, Armando877c31fc-2194-40ff-9e77-bbda0b355fcb3002019-07-02T18:49:02Z2019-07-02T18:49:02Z2015-09-01ISSN: 2346-2183https://repositorio.unal.edu.co/handle/unal/60657http://bdigital.unal.edu.co/58989/Time and cost overruns in highway construction are usual in Colombia. Contractors regularly fail in cost estimation and construction scheduling. An analysis of important factors on time and cost overruns in highway construction in southwest Colombia is presented in this paper. Forty highway construction projects were reviewed. Data from construction documents were collected to prepare a data base for probabilistic analysis. Data collected include scheduled construction time and cost, actual construction time and cost, and unexpected events which could have affected the construction process. Data were used in a probabilistic cost and schedule risk analysis to identify critical factors in construction time and cost overruns in the region. It was found that the activities that most affect the time and cost overruns are the construction of the granular base and the asphalt layer. The most common causes of construction overruns were found to be poor cost and duration estimates, rain, and materials supply problems.application/pdfspaUniversidad Nacional de Colombia (Sede Medellín). Facultad de Minas.https://revistas.unal.edu.co/index.php/dyna/article/view/47453Universidad Nacional de Colombia Revistas electrónicas UN DynaDynaGómez, Hernán Darío and Orobio, Armando (2015) Effects of uncertainty on scheduling of highway construction projects. DYNA, 82 (193). pp. 155-164. ISSN 2346-218362 Ingeniería y operaciones afines / EngineeringHighway Infrastructureconstruction schedulingtime overruncost overrunEffects of uncertainty on scheduling of highway construction projectsArtículo de revistainfo:eu-repo/semantics/articleinfo:eu-repo/semantics/publishedVersionhttp://purl.org/coar/resource_type/c_6501http://purl.org/coar/resource_type/c_2df8fbb1http://purl.org/coar/version/c_970fb48d4fbd8a85Texthttp://purl.org/redcol/resource_type/ARTORIGINAL47453-264011-1-PB.pdfapplication/pdf1562161https://repositorio.unal.edu.co/bitstream/unal/60657/1/47453-264011-1-PB.pdf2a8b047145889cf404cd2e02479fa3d2MD51THUMBNAIL47453-264011-1-PB.pdf.jpg47453-264011-1-PB.pdf.jpgGenerated Thumbnailimage/jpeg8837https://repositorio.unal.edu.co/bitstream/unal/60657/2/47453-264011-1-PB.pdf.jpg9d16c9ef3430aac823f4d63777f27df4MD52unal/60657oai:repositorio.unal.edu.co:unal/606572024-04-14 23:11:25.226Repositorio Institucional Universidad Nacional de Colombiarepositorio_nal@unal.edu.co |
dc.title.spa.fl_str_mv |
Effects of uncertainty on scheduling of highway construction projects |
title |
Effects of uncertainty on scheduling of highway construction projects |
spellingShingle |
Effects of uncertainty on scheduling of highway construction projects 62 Ingeniería y operaciones afines / Engineering Highway Infrastructure construction scheduling time overrun cost overrun |
title_short |
Effects of uncertainty on scheduling of highway construction projects |
title_full |
Effects of uncertainty on scheduling of highway construction projects |
title_fullStr |
Effects of uncertainty on scheduling of highway construction projects |
title_full_unstemmed |
Effects of uncertainty on scheduling of highway construction projects |
title_sort |
Effects of uncertainty on scheduling of highway construction projects |
dc.creator.fl_str_mv |
Gómez, Hernán Darío Orobio, Armando |
dc.contributor.author.spa.fl_str_mv |
Gómez, Hernán Darío Orobio, Armando |
dc.subject.ddc.spa.fl_str_mv |
62 Ingeniería y operaciones afines / Engineering |
topic |
62 Ingeniería y operaciones afines / Engineering Highway Infrastructure construction scheduling time overrun cost overrun |
dc.subject.proposal.spa.fl_str_mv |
Highway Infrastructure construction scheduling time overrun cost overrun |
description |
Time and cost overruns in highway construction are usual in Colombia. Contractors regularly fail in cost estimation and construction scheduling. An analysis of important factors on time and cost overruns in highway construction in southwest Colombia is presented in this paper. Forty highway construction projects were reviewed. Data from construction documents were collected to prepare a data base for probabilistic analysis. Data collected include scheduled construction time and cost, actual construction time and cost, and unexpected events which could have affected the construction process. Data were used in a probabilistic cost and schedule risk analysis to identify critical factors in construction time and cost overruns in the region. It was found that the activities that most affect the time and cost overruns are the construction of the granular base and the asphalt layer. The most common causes of construction overruns were found to be poor cost and duration estimates, rain, and materials supply problems. |
publishDate |
2015 |
dc.date.issued.spa.fl_str_mv |
2015-09-01 |
dc.date.accessioned.spa.fl_str_mv |
2019-07-02T18:49:02Z |
dc.date.available.spa.fl_str_mv |
2019-07-02T18:49:02Z |
dc.type.spa.fl_str_mv |
Artículo de revista |
dc.type.coar.fl_str_mv |
http://purl.org/coar/resource_type/c_2df8fbb1 |
dc.type.driver.spa.fl_str_mv |
info:eu-repo/semantics/article |
dc.type.version.spa.fl_str_mv |
info:eu-repo/semantics/publishedVersion |
dc.type.coar.spa.fl_str_mv |
http://purl.org/coar/resource_type/c_6501 |
dc.type.coarversion.spa.fl_str_mv |
http://purl.org/coar/version/c_970fb48d4fbd8a85 |
dc.type.content.spa.fl_str_mv |
Text |
dc.type.redcol.spa.fl_str_mv |
http://purl.org/redcol/resource_type/ART |
format |
http://purl.org/coar/resource_type/c_6501 |
status_str |
publishedVersion |
dc.identifier.issn.spa.fl_str_mv |
ISSN: 2346-2183 |
dc.identifier.uri.none.fl_str_mv |
https://repositorio.unal.edu.co/handle/unal/60657 |
dc.identifier.eprints.spa.fl_str_mv |
http://bdigital.unal.edu.co/58989/ |
identifier_str_mv |
ISSN: 2346-2183 |
url |
https://repositorio.unal.edu.co/handle/unal/60657 http://bdigital.unal.edu.co/58989/ |
dc.language.iso.spa.fl_str_mv |
spa |
language |
spa |
dc.relation.spa.fl_str_mv |
https://revistas.unal.edu.co/index.php/dyna/article/view/47453 |
dc.relation.ispartof.spa.fl_str_mv |
Universidad Nacional de Colombia Revistas electrónicas UN Dyna Dyna |
dc.relation.references.spa.fl_str_mv |
Gómez, Hernán Darío and Orobio, Armando (2015) Effects of uncertainty on scheduling of highway construction projects. DYNA, 82 (193). pp. 155-164. ISSN 2346-2183 |
dc.rights.spa.fl_str_mv |
Derechos reservados - Universidad Nacional de Colombia |
dc.rights.coar.fl_str_mv |
http://purl.org/coar/access_right/c_abf2 |
dc.rights.license.spa.fl_str_mv |
Atribución-NoComercial 4.0 Internacional |
dc.rights.uri.spa.fl_str_mv |
http://creativecommons.org/licenses/by-nc/4.0/ |
dc.rights.accessrights.spa.fl_str_mv |
info:eu-repo/semantics/openAccess |
rights_invalid_str_mv |
Atribución-NoComercial 4.0 Internacional Derechos reservados - Universidad Nacional de Colombia http://creativecommons.org/licenses/by-nc/4.0/ http://purl.org/coar/access_right/c_abf2 |
eu_rights_str_mv |
openAccess |
dc.format.mimetype.spa.fl_str_mv |
application/pdf |
dc.publisher.spa.fl_str_mv |
Universidad Nacional de Colombia (Sede Medellín). Facultad de Minas. |
institution |
Universidad Nacional de Colombia |
bitstream.url.fl_str_mv |
https://repositorio.unal.edu.co/bitstream/unal/60657/1/47453-264011-1-PB.pdf https://repositorio.unal.edu.co/bitstream/unal/60657/2/47453-264011-1-PB.pdf.jpg |
bitstream.checksum.fl_str_mv |
2a8b047145889cf404cd2e02479fa3d2 9d16c9ef3430aac823f4d63777f27df4 |
bitstream.checksumAlgorithm.fl_str_mv |
MD5 MD5 |
repository.name.fl_str_mv |
Repositorio Institucional Universidad Nacional de Colombia |
repository.mail.fl_str_mv |
repositorio_nal@unal.edu.co |
_version_ |
1814089414258720768 |