Engineering Innovation of a Length of Nearly 3300m large Diameter Pipeline Installed by HDD

The Yangtze River Crossing Project, which is part of the Chinese gas pipeline trunk network and aims to transmit the natural gas to the Yangtze River Delta area, sets up a record for the length of Horizontal Directional Drilling (HDD) in the world. The term of pipeline installed is 3300m, and the di...

Full description

Autores:
Guohui, Li
Xiaocheng, Ma
Chunling, Yang
Tipo de recurso:
Article of journal
Fecha de publicación:
2016
Institución:
Universidad Nacional de Colombia
Repositorio:
Universidad Nacional de Colombia
Idioma:
spa
OAI Identifier:
oai:repositorio.unal.edu.co:unal/63637
Acceso en línea:
https://repositorio.unal.edu.co/handle/unal/63637
http://bdigital.unal.edu.co/64083/
Palabra clave:
55 Ciencias de la tierra / Earth sciences and geology
Engineering Innovation
Long distance
Large diameter
Gas Pipeline
Horizontal Directional Drilling (HDD)
Starting Velocity.
Rights
openAccess
License
Atribución-NoComercial 4.0 Internacional
id UNACIONAL2_d49493112ccf75aaec6f6b8aada61e7d
oai_identifier_str oai:repositorio.unal.edu.co:unal/63637
network_acronym_str UNACIONAL2
network_name_str Universidad Nacional de Colombia
repository_id_str
spelling Atribución-NoComercial 4.0 InternacionalDerechos reservados - Universidad Nacional de Colombiahttp://creativecommons.org/licenses/by-nc/4.0/info:eu-repo/semantics/openAccesshttp://purl.org/coar/access_right/c_abf2Guohui, Li1f08b7be-ea3f-45b7-8d29-0fe16eb5a6f2300Xiaocheng, Mae2eeefe9-ba02-4e12-9424-4c0690224c22300Chunling, Yangd0baf08d-59d0-490a-bb07-2c00ec8333a73002019-07-02T21:58:52Z2019-07-02T21:58:52Z2016-01-01ISSN: 2339-3459https://repositorio.unal.edu.co/handle/unal/63637http://bdigital.unal.edu.co/64083/The Yangtze River Crossing Project, which is part of the Chinese gas pipeline trunk network and aims to transmit the natural gas to the Yangtze River Delta area, sets up a record for the length of Horizontal Directional Drilling (HDD) in the world. The term of pipeline installed is 3300m, and the diameter is 40in. Many technical difficulties have been inevitably encountered in a large diameter hole reaming in fine sand, the calculation of section scour depth which determines the minimum buried depth of the pipe, protection of outside coating and the method of long distance pilot hole drilling, such other challenges. In view of this, it was recommended that two pipelines of 711mm should be installed to replace the existing one of 1016mm in diameter and 1% flooding scour depth obtained by reliable statistical analysis. In period of installation, application glass fiber reinforced epoxy resin as a protective coating, executing the pilot hole by Intersect Method. As a result, this super project is finished successfully on May 21.2013. The experience can be applied to any pipeline engineering the installed by horizontal directional drilling or similar works.application/pdfspaUniversidad Nacional de Colombia - Sede Bogotá - Facultad de Ciencias - Departamento de Geocienciahttps://revistas.unal.edu.co/index.php/esrj/article/view/54504Universidad Nacional de Colombia Revistas electrónicas UN Earth Sciences Research JournalEarth Sciences Research JournalGuohui, Li and Xiaocheng, Ma and Chunling, Yang (2016) Engineering Innovation of a Length of Nearly 3300m large Diameter Pipeline Installed by HDD. Earth Sciences Research Journal, 20 (1). P1-P5. ISSN 2339-345955 Ciencias de la tierra / Earth sciences and geologyEngineering InnovationLong distanceLarge diameterGas PipelineHorizontal Directional Drilling (HDD)Starting Velocity.Engineering Innovation of a Length of Nearly 3300m large Diameter Pipeline Installed by HDDArtículo de revistainfo:eu-repo/semantics/articleinfo:eu-repo/semantics/publishedVersionhttp://purl.org/coar/resource_type/c_6501http://purl.org/coar/resource_type/c_2df8fbb1http://purl.org/coar/version/c_970fb48d4fbd8a85Texthttp://purl.org/redcol/resource_type/ARTORIGINAL54504-290724-1-PB.pdfapplication/pdf1436764https://repositorio.unal.edu.co/bitstream/unal/63637/1/54504-290724-1-PB.pdf3f5fddd3d57e041b5808db6873b52b0aMD51THUMBNAIL54504-290724-1-PB.pdf.jpg54504-290724-1-PB.pdf.jpgGenerated Thumbnailimage/jpeg8119https://repositorio.unal.edu.co/bitstream/unal/63637/2/54504-290724-1-PB.pdf.jpg8878d59c4ce8b47440119f669e4ba02eMD52unal/63637oai:repositorio.unal.edu.co:unal/636372023-04-22 23:05:56.016Repositorio Institucional Universidad Nacional de Colombiarepositorio_nal@unal.edu.co
dc.title.spa.fl_str_mv Engineering Innovation of a Length of Nearly 3300m large Diameter Pipeline Installed by HDD
title Engineering Innovation of a Length of Nearly 3300m large Diameter Pipeline Installed by HDD
spellingShingle Engineering Innovation of a Length of Nearly 3300m large Diameter Pipeline Installed by HDD
55 Ciencias de la tierra / Earth sciences and geology
Engineering Innovation
Long distance
Large diameter
Gas Pipeline
Horizontal Directional Drilling (HDD)
Starting Velocity.
title_short Engineering Innovation of a Length of Nearly 3300m large Diameter Pipeline Installed by HDD
title_full Engineering Innovation of a Length of Nearly 3300m large Diameter Pipeline Installed by HDD
title_fullStr Engineering Innovation of a Length of Nearly 3300m large Diameter Pipeline Installed by HDD
title_full_unstemmed Engineering Innovation of a Length of Nearly 3300m large Diameter Pipeline Installed by HDD
title_sort Engineering Innovation of a Length of Nearly 3300m large Diameter Pipeline Installed by HDD
dc.creator.fl_str_mv Guohui, Li
Xiaocheng, Ma
Chunling, Yang
dc.contributor.author.spa.fl_str_mv Guohui, Li
Xiaocheng, Ma
Chunling, Yang
dc.subject.ddc.spa.fl_str_mv 55 Ciencias de la tierra / Earth sciences and geology
topic 55 Ciencias de la tierra / Earth sciences and geology
Engineering Innovation
Long distance
Large diameter
Gas Pipeline
Horizontal Directional Drilling (HDD)
Starting Velocity.
dc.subject.proposal.spa.fl_str_mv Engineering Innovation
Long distance
Large diameter
Gas Pipeline
Horizontal Directional Drilling (HDD)
Starting Velocity.
description The Yangtze River Crossing Project, which is part of the Chinese gas pipeline trunk network and aims to transmit the natural gas to the Yangtze River Delta area, sets up a record for the length of Horizontal Directional Drilling (HDD) in the world. The term of pipeline installed is 3300m, and the diameter is 40in. Many technical difficulties have been inevitably encountered in a large diameter hole reaming in fine sand, the calculation of section scour depth which determines the minimum buried depth of the pipe, protection of outside coating and the method of long distance pilot hole drilling, such other challenges. In view of this, it was recommended that two pipelines of 711mm should be installed to replace the existing one of 1016mm in diameter and 1% flooding scour depth obtained by reliable statistical analysis. In period of installation, application glass fiber reinforced epoxy resin as a protective coating, executing the pilot hole by Intersect Method. As a result, this super project is finished successfully on May 21.2013. The experience can be applied to any pipeline engineering the installed by horizontal directional drilling or similar works.
publishDate 2016
dc.date.issued.spa.fl_str_mv 2016-01-01
dc.date.accessioned.spa.fl_str_mv 2019-07-02T21:58:52Z
dc.date.available.spa.fl_str_mv 2019-07-02T21:58:52Z
dc.type.spa.fl_str_mv Artículo de revista
dc.type.coar.fl_str_mv http://purl.org/coar/resource_type/c_2df8fbb1
dc.type.driver.spa.fl_str_mv info:eu-repo/semantics/article
dc.type.version.spa.fl_str_mv info:eu-repo/semantics/publishedVersion
dc.type.coar.spa.fl_str_mv http://purl.org/coar/resource_type/c_6501
dc.type.coarversion.spa.fl_str_mv http://purl.org/coar/version/c_970fb48d4fbd8a85
dc.type.content.spa.fl_str_mv Text
dc.type.redcol.spa.fl_str_mv http://purl.org/redcol/resource_type/ART
format http://purl.org/coar/resource_type/c_6501
status_str publishedVersion
dc.identifier.issn.spa.fl_str_mv ISSN: 2339-3459
dc.identifier.uri.none.fl_str_mv https://repositorio.unal.edu.co/handle/unal/63637
dc.identifier.eprints.spa.fl_str_mv http://bdigital.unal.edu.co/64083/
identifier_str_mv ISSN: 2339-3459
url https://repositorio.unal.edu.co/handle/unal/63637
http://bdigital.unal.edu.co/64083/
dc.language.iso.spa.fl_str_mv spa
language spa
dc.relation.spa.fl_str_mv https://revistas.unal.edu.co/index.php/esrj/article/view/54504
dc.relation.ispartof.spa.fl_str_mv Universidad Nacional de Colombia Revistas electrónicas UN Earth Sciences Research Journal
Earth Sciences Research Journal
dc.relation.references.spa.fl_str_mv Guohui, Li and Xiaocheng, Ma and Chunling, Yang (2016) Engineering Innovation of a Length of Nearly 3300m large Diameter Pipeline Installed by HDD. Earth Sciences Research Journal, 20 (1). P1-P5. ISSN 2339-3459
dc.rights.spa.fl_str_mv Derechos reservados - Universidad Nacional de Colombia
dc.rights.coar.fl_str_mv http://purl.org/coar/access_right/c_abf2
dc.rights.license.spa.fl_str_mv Atribución-NoComercial 4.0 Internacional
dc.rights.uri.spa.fl_str_mv http://creativecommons.org/licenses/by-nc/4.0/
dc.rights.accessrights.spa.fl_str_mv info:eu-repo/semantics/openAccess
rights_invalid_str_mv Atribución-NoComercial 4.0 Internacional
Derechos reservados - Universidad Nacional de Colombia
http://creativecommons.org/licenses/by-nc/4.0/
http://purl.org/coar/access_right/c_abf2
eu_rights_str_mv openAccess
dc.format.mimetype.spa.fl_str_mv application/pdf
dc.publisher.spa.fl_str_mv Universidad Nacional de Colombia - Sede Bogotá - Facultad de Ciencias - Departamento de Geociencia
institution Universidad Nacional de Colombia
bitstream.url.fl_str_mv https://repositorio.unal.edu.co/bitstream/unal/63637/1/54504-290724-1-PB.pdf
https://repositorio.unal.edu.co/bitstream/unal/63637/2/54504-290724-1-PB.pdf.jpg
bitstream.checksum.fl_str_mv 3f5fddd3d57e041b5808db6873b52b0a
8878d59c4ce8b47440119f669e4ba02e
bitstream.checksumAlgorithm.fl_str_mv MD5
MD5
repository.name.fl_str_mv Repositorio Institucional Universidad Nacional de Colombia
repository.mail.fl_str_mv repositorio_nal@unal.edu.co
_version_ 1806886117425807360