Ajustes al mecanismo de cargo por confiabilidad del sector eléctrico colombiano
En todo mercado de electricidad, es fundamental poder suministrar la energía demandada por las personas y empresas, a cualquier hora y en cualquier período del año. Sin embargo, en países como Colombia cuya matriz energética está fuertemente ligada a la generación de energía hidroeléctrica hay condi...
- Autores:
-
Castrillon Charari, Lady Snedy
- Tipo de recurso:
- Fecha de publicación:
- 2024
- Institución:
- Universidad Nacional de Colombia
- Repositorio:
- Universidad Nacional de Colombia
- Idioma:
- spa
- OAI Identifier:
- oai:repositorio.unal.edu.co:unal/85812
- Palabra clave:
- 620 - Ingeniería y operaciones afines
330 - Economía::333 - Economía de la tierra y de la energía
Energía eléctrica - Colombia
Sector energético - Colombia
Demanda de energía - Colombia
Consumo de energía - Colombia
Capacitancia
Recursos energéticos - Colombia
Abastecimiento de energía - Colombia
Economía de la energía - Colombia
Cargo por confiabilidad
Mercado de capacidad
Sector eléctrico
Matriz energética
Suministro
Reliability charge
Capacity market
Electricity sector
Energy matrix
Supply
- Rights
- openAccess
- License
- Reconocimiento 4.0 Internacional
id |
UNACIONAL2_7a7edb62cd419a3c4e7b9dd0b5b58a41 |
---|---|
oai_identifier_str |
oai:repositorio.unal.edu.co:unal/85812 |
network_acronym_str |
UNACIONAL2 |
network_name_str |
Universidad Nacional de Colombia |
repository_id_str |
|
dc.title.spa.fl_str_mv |
Ajustes al mecanismo de cargo por confiabilidad del sector eléctrico colombiano |
dc.title.translated.eng.fl_str_mv |
Adjustments to the reliability charge mechanism in the Colombian electricity sector |
title |
Ajustes al mecanismo de cargo por confiabilidad del sector eléctrico colombiano |
spellingShingle |
Ajustes al mecanismo de cargo por confiabilidad del sector eléctrico colombiano 620 - Ingeniería y operaciones afines 330 - Economía::333 - Economía de la tierra y de la energía Energía eléctrica - Colombia Sector energético - Colombia Demanda de energía - Colombia Consumo de energía - Colombia Capacitancia Recursos energéticos - Colombia Abastecimiento de energía - Colombia Economía de la energía - Colombia Cargo por confiabilidad Mercado de capacidad Sector eléctrico Matriz energética Suministro Reliability charge Capacity market Electricity sector Energy matrix Supply |
title_short |
Ajustes al mecanismo de cargo por confiabilidad del sector eléctrico colombiano |
title_full |
Ajustes al mecanismo de cargo por confiabilidad del sector eléctrico colombiano |
title_fullStr |
Ajustes al mecanismo de cargo por confiabilidad del sector eléctrico colombiano |
title_full_unstemmed |
Ajustes al mecanismo de cargo por confiabilidad del sector eléctrico colombiano |
title_sort |
Ajustes al mecanismo de cargo por confiabilidad del sector eléctrico colombiano |
dc.creator.fl_str_mv |
Castrillon Charari, Lady Snedy |
dc.contributor.advisor.none.fl_str_mv |
Franco Cardona, Carlos Jaime |
dc.contributor.author.none.fl_str_mv |
Castrillon Charari, Lady Snedy |
dc.subject.ddc.spa.fl_str_mv |
620 - Ingeniería y operaciones afines 330 - Economía::333 - Economía de la tierra y de la energía |
topic |
620 - Ingeniería y operaciones afines 330 - Economía::333 - Economía de la tierra y de la energía Energía eléctrica - Colombia Sector energético - Colombia Demanda de energía - Colombia Consumo de energía - Colombia Capacitancia Recursos energéticos - Colombia Abastecimiento de energía - Colombia Economía de la energía - Colombia Cargo por confiabilidad Mercado de capacidad Sector eléctrico Matriz energética Suministro Reliability charge Capacity market Electricity sector Energy matrix Supply |
dc.subject.lemb.none.fl_str_mv |
Energía eléctrica - Colombia Sector energético - Colombia Demanda de energía - Colombia Consumo de energía - Colombia Capacitancia Recursos energéticos - Colombia Abastecimiento de energía - Colombia Economía de la energía - Colombia |
dc.subject.proposal.spa.fl_str_mv |
Cargo por confiabilidad Mercado de capacidad Sector eléctrico Matriz energética Suministro |
dc.subject.proposal.eng.fl_str_mv |
Reliability charge Capacity market Electricity sector Energy matrix Supply |
description |
En todo mercado de electricidad, es fundamental poder suministrar la energía demandada por las personas y empresas, a cualquier hora y en cualquier período del año. Sin embargo, en países como Colombia cuya matriz energética está fuertemente ligada a la generación de energía hidroeléctrica hay condiciones externas como los regímenes hidrológicos que se vuelven determinantes para la generación de energía. Por tanto, surgen mecanismos como el cargo por confiabilidad, que busca garantizar la disponibilidad energética en épocas críticas al contratar obligaciones de energía firme con los generadores. A pesar de esto, en épocas climáticas críticas, el país ha estado a punto de racionar debido a que el cargo por confiabilidad no ha funcionado como se esperaba, y se han tenido que implementar otros mecanismos para asegurar atención de la demanda. Por esto, esta propuesta de trabajo final está enfocada en proponer ajustes al actual mecanismo de cargo por confiabilidad del sector eléctrico colombiano. Para lograr esto, se propone inicialmente hacer una revisión exploratoria para algunos países con relación a los mercados de capacidad, donde se recopile información más amplia acerca de su normativa, sus métodos, su funcionamiento y su financiamiento; con el fin de realizar un análisis cuantitativo y cualitativo de los datos; para entender su desarrollo y falencias, y así plantear finalmente cuáles son los ajustes necesarios para que el actual cargo por confiabilidad funcione de una manera más eficiente en el mercado eléctrico local. (Tomado de la fuente) |
publishDate |
2024 |
dc.date.accessioned.none.fl_str_mv |
2024-03-15T15:47:26Z |
dc.date.available.none.fl_str_mv |
2024-03-15T15:47:26Z |
dc.date.issued.none.fl_str_mv |
2024-12-30 |
dc.type.spa.fl_str_mv |
Trabajo de grado - Maestría |
dc.type.driver.spa.fl_str_mv |
info:eu-repo/semantics/masterThesis |
dc.type.version.spa.fl_str_mv |
info:eu-repo/semantics/acceptedVersion |
dc.type.content.spa.fl_str_mv |
Text |
dc.type.redcol.spa.fl_str_mv |
http://purl.org/redcol/resource_type/TM |
status_str |
acceptedVersion |
dc.identifier.uri.none.fl_str_mv |
https://repositorio.unal.edu.co/handle/unal/85812 |
dc.identifier.instname.spa.fl_str_mv |
Universidad Nacional de Colombia |
dc.identifier.reponame.spa.fl_str_mv |
Repositorio Institucional Universidad Nacional de Colombia |
dc.identifier.repourl.spa.fl_str_mv |
https://repositorio.unal.edu.co/ |
url |
https://repositorio.unal.edu.co/handle/unal/85812 https://repositorio.unal.edu.co/ |
identifier_str_mv |
Universidad Nacional de Colombia Repositorio Institucional Universidad Nacional de Colombia |
dc.language.iso.spa.fl_str_mv |
spa |
language |
spa |
dc.relation.indexed.spa.fl_str_mv |
LaReferencia |
dc.relation.references.spa.fl_str_mv |
AEMO. (2023a). Wholesale Electricity Market Design Summary. AEMO. (2023b). About the Wholesale Electricity Market (WEM). Aemo.Com.Au. https://aemo.com.au/energy-systems/electricity/wholesale-electricity-market-wem/about the-wholesale-electricity-market-wa-wem AEMO. (2023c). Reserve Capacity Price. Aemo.Com.Au. https://aemo.com.au/energy systems/electricity/wholesale-electricity-market-wem/wa-reserve-capacity mechanism/reserve-capacity-price#:~:text=The administrative Reserve Capacity Price,set in the WEM Rules. AEMO. (2023d). Reserve Capacity Price. Aemo.Com.Au. https://aemo.com.au/energy systems/electricity/wholesale-electricity-market-wem/wa-reserve-capacity mechanism/reserve-capacity-price#:~:text=The administrative Reserve Capacity Price,set in the WEM Rules. AEMO. (2023e). Wholesale Electricity Market (WEM). Aemo.Com.Au. https://aemo.com.au/energy-systems/electricity/wholesale-electricity-market-wem ANDEG. (2017). Un segundo análisis del precio de escasez. Andrés, O., Morales, C., Andrés, J., Gil, M., De, G., Upme, G., Beleño, L. A. H., Aldana, A., Henry, U., Zapata, J., Segura López, A., Fernando, C., Franco, V., Hernando, M., Ruiz, M., Tobías, F., & Cañón, O. (2023). Plan Indicativo de Expansión de la Generación. Anuta, O. H., Taylor, P., Jones, D., McEntee, T., & Wade, N. (2014). An international review of the implications of regulatory and electricity market structures on the emergence of grid scale electricity storage. Renewable and Sustainable Energy Reviews, 38, 489–508. https://doi.org/10.1016/j.rser.2014.06.006 Arango, S., López, J. A., Medina, G., Domínguez, E., Uribe, E., Zapata, W., Martínez, J. F., & Correa, C. (2013). Estudio para determinar la vulnerabilidad y las opciones de adaptación del sector energético colombiano frente al cambio climático Arango, S., Restrepo, M. I., & Vélez, L. G. (2011). La confiabilidad en los sistemas eléctricos competitivos y el modelo colombiano de cargo por confiabilidad. Cuadernos de Economía, 31(56), 199–223. Asmar, S. (2022, September 15). Diversificar la matriz y cuidado del planeta, hacia una transición energética justa y sostenible. Larepublica.Co/. Australian Government. (2023). National Electricity Market. Energy.Gov.Au. https://www.energy.gov.au/government-priorities/energy-markets/national-electricity market-nem Bedoya, J. C., Rodas, E. A., & García, D. F. (2016). Descripción de los Aspectos Comerciales del Esquema del Cargo por Confiabilidad en el Mercado Eléctrico Colombiano. Scientia et Technica , 21(1), 5–14. Bell, P. L. (2012). Geografia, Topografia y Clima Colombia. Colombia : Manual Comercial e Industrial, 37–50. Bersano, L., & Paredes, J. R. (2017). En Colombia, el fenómeno del Niño, nos pone a prueba. Blogs.Iadb.Org. https://blogs.iadb.org/energia/es/2406/ Bloomberg. (2023, June 16). El gas, el “salvavidas” de Venezuela para reactivar su economía. Portafolio. Brigard Urrutia. (2023). CREG define fecha de asignación para el Cargo por Confiabilidad. Bu.Com.Co. https://www.bu.com.co/es/insights/noticias/creg-define-fecha-de-asignacion para-el-cargo-por-confiabilidad Carabott, M., & Wallington, B. (2022). WA capacity charges – What are they, and how can they reduce my electricity bill. Leadingedgeenergy.Com.Au. https://www.leadingedgeenergy.com.au/blog/wa-capacity-charges/ Cárdena, T. (2017). El Niño, la crisis energética y las lecciones que se aprendieron. El Eafitense. https://www.eafit.edu.co/medios/eleafitense/110/Paginas/el-nino-crisis-energetica.aspx Celsia Energía. (2021). Documento de trabajo sobre el Sistema Interconectado Nacional, SIN. 1–4. Chacón, M. (2023, November 6). Fenómeno de El Niño inicia oficialmente: su mayor intensidad empezaría desde noviembre. El Tiempo. https://www.eltiempo.com/vida/medio ambiente/fenomeno-de-el-nino-inicia-oficialmente-su-mayor-intensidad-empezaria-desde noviembre-823093#:~:text=Mateo%20Chac%C3%B3n%20Orduz- ,06%20de%20noviembre%202023%2C%2012%3A00%20A.,M.&text=El%20Instituto%20de%2 0Hidrolog%C3%ADa%2C%20Meteorolog%C3%ADa,t%C3%A9cnicos%20para%20esta%20decl aratoria%20oficial. Chestney, N. (2022, February 16). UK electricity capacity auction clears at highest ever price. Reuters. https://www.reuters.com/world/uk/uk-electricity-capacity-auction-clears-highest ever-price-2022-02-16/ CNN Español. (2022). ¿Por qué el dólar estadounidense es la principal moneda del mundo? Cnnespanol.Cnn.Com. https://cnnespanol.cnn.com/2022/08/08/por-que-el-dolar estadounidense-es-la-principal-moneda-del-mundo-orix Comisión de Regulación de Energía y Gas. (1996). Cargo por capacidad. Comisión de Regulación de Energía y Gas. (2007). Resolución No.071 ( 03 ct. 2006 ). http://apolo.creg.gov.co/Publicac.nsf/1c09d18d2d5ffb5b05256eee00709c02/243937481e51 77820525785a007a6f75?OpenDocument#:~:text=Cargo por Confiabilidad%3A Remuneración que,Subasta para la Asignación de Comisión de Regulación de Energía y Gas. (2016). ALTERNATIVAS PARA DEFINIR EL PRECIO DE ESCASEZ. Comisión de Regulación de Energía y Gas. (2023a). Energía firme para el cargo por confiabilidad (enficc). https://www.creg.gov.co/ Comisión de Regulación de Energía y Gas. (2023b). Historia en Colombia. CREG.Gov.Co. Consulting, C. (2020). Capacity markets and energy-only markets-a survey of recent developments. February, 46 Contraloría General de la República. (2016b). Informe de resultados de la actuacion especial de fiscalización sobre el manejo de recursos del cargo por confiabilidad. 1, 1–57. https://observatoriofiscal.contraloria.gov.co/Publicaciones/El Manejo de Recursos del Cargo por Confiabilidad.pdf Contreras, D. (2016). El impacto de El Niño en Colombia. Fasecolda, 42–46. Cour des Comptes. (2022). Organisation of the Electricity Markets (Issue July). Cramton, P., & Ockenfels, A. (2012). Economics and Design of Capacity Markets for the Power Sector. Zeitschrift Für Energiewirtschaft, 36(2), 113–134. https://doi.org/10.1007/s12398- 012-0084-2 CREG. (2006a). Cargo por Confiabilidad. 87. CREG. (2006b). Cargo por Confiabilidad. 87. http://www.xm.com.co/Promocin Primera Subasta de Energa Firme/abc2.pdf CREG. (2024). Compilación del Cargo por Confiabilidad en el Mercado Mayorista de Energía Eléctrica. https://gestornormativo.creg.gov.co/gestor/entorno/docs/ru_creg_cc.htm Dahiru, A. T., Daud, D., Tan, C. W., Jagun, Z. T., Samsudin, S., & Dobi, A. M. (2023). A comprehensive review of demand side management in distributed grids based on real estate perspectives. Environmental Science and Pollution Research. https://doi.org/10.1007/s11356-023-25146-x Datosmacros.com. (2023). Población. Datosmacro.Expansion.Com. https://datosmacro.expansion.com/demografia/poblacion Duque, J. P. B., García, J. J., & Velásquez, H. (2016). Efectos del cargo por confiabilidad sobre el precio spot de la energía eléctrica en colombia. Cuadernos de Economia (Colombia), 35(68), 491–519. https://doi.org/10.15446/cuad.econ.v35n68.52732 Dyner, I., Franco, C. J., Cadavid, L., García, A., Giraldo, E. A., Giraldo, J. E., Gómez, D. F., Nieto, M. J., Rodríguez, R., & Quiceno, G. (2018). Ocaso de un paradigma. Hacia un nuevo modelo eléctrico (I. Dyner & C. J. Franco, Eds.; Primera). Fondo de Cultura Económica, Universidad de Bogotá Jorge Tadeo Lozano. EIA. (2023). Electricity in the United States. U.S. Energy Information Administration. https://www.eia.gov/energyexplained/electricity/electricity-in-the-us.php El Heraldo. (2016). “Daño en Termoflores aumenta riesgo de apagón”: Andeg. El Heraldo. Enel. (2023). Descripción del Mercado. Así Llega La Energía y El Gas a Tu Empresa. https://www.enel.com.co/es/empresas/enel-generacion/como-se-genera-la-electricidad.html Enerdata. (2023a). Producción de electricidad. Enerdata. https://datos.enerdata.net/electricidad/estadisticas-mundiales-produccion-electricidad.html Enerdata. (2023b). Producción de gas natural. Datos.Enerdata.Net. https://datos.enerdata.net/gas-natural/produccion-gas-natural-mundial.html Energy UK. (2023). Electricity generation. Energy-Uk.Org.Uk. https://www.energy uk.org.uk/insights/electricity-generation/ EPA. (2023a). Power Market Structure. Epa.Gov. https://www.epa.gov/green-power markets/power-market-structure EPA. (2023b). The U.S. Electricity System. About the U.S. Electricity System and Its Impact on the Environment. https://www.epa.gov/energy/about-us-electricity-system-and-its-impact environment#:~:text=Electricity in the United States,generated at centralized power plants. Estrada, M. P., Duque, B. M., & Rendón, J. J. (2017). Análisis comparativo de diferentes esquemas de suficiencia en generación eléctrica: Algunas reflexiones para el mercado eléctrico en Colombia. Energy, 16, 1–33. Flexcity. (2021a). Increase in the prices of the French Capacity Mechanism auction. Flexcity.Energy. https://www.flexcity.energy/it/increase-the-prices-of-the-french-capacity-mechanism auction Flexcity. (2021b). Increase in the prices of the French Capacity Mechanism auction. Flexcity.Energy. https://www.flexcity.energy/it/increase-the-prices-of-the-french-capacity-mechanism-auction Flexitricity. (2023). Capacity Market. Flexitricity.Com. https://flexitricity.com/services/capacity-market/#:~:text=The Capacity Market (CM) was,System Stress Event could occur. Franco, C. J. (2023). Los Mercados Mayoristas de Electricidad Estructura y Comercialización (pp. 1– 26). Fundación Endesa. (2023a). Central térmica convencional. https://www.fundacionendesa.org/ Garcés, E. (2013). Evaluación de políticas para garantizar el abastecimiento de energía eléctrica en Colombia. García, L. F. (2023, April 19). Plenaria aprueba prohibición del fracking en Colombia. Senado.Gov.Co. https://www.senado.gov.co/index.php/el-senado/noticias/4468-plenaria aprueba-prohibicion-del-fracking-en-colombia Geoscience Australia. (2023). Overviw. Ga.Gov.Au. https://www.ga.gov.au/scientific-topics/energy/overview Grupo Banco Mundial. (2023). Población total. Banco Mundial. https://datos.bancomundial.org/indicator/SP.POP.TOTL?most_recent_value_desc=true Heaton, A. (2022). Chapter 4: Natural Gas Chart 4.1 Supply and demand for natural. https://assets.publishing.service.gov.uk/ Howorth, N., Pay, J., Shepherd, J., & Coxall, M. (2015). Capacity Market: an EMR Primer. https://www.cliffordchance.com/ Hurtado, J. I. (2014). Cronología del sector eléctrico colombiano. Revista de Santander, 9, 22. Ideam. (2023). Fenómenos del Niño y la Niña. Ministerio de Ambiente y Desarrollo Sostenible de Colombia. http://www.ideam.gov.co/web/siac/ninoynina IEA. (2023a). Australia. Iea.Org. https://www.iea.org/countries/australia IEA. (2023b). France. Iea.Org. https://www.iea.org/countries/france IEA. (2023c). United Kingdom. Iea.Org. https://www.iea.org/countries/united-kingdom Institute for Government. (2022). Electricity market. Instituteforgovernment.Org.Uk. https://www.instituteforgovernment.org.uk/article/explainer/electricity-market Invinity Energy Systems. (2023). What the 2022 T-1 Capacity Market Auction Tells Us About Wholesale Market Prices for Energy Storage. Invinity.Com. https://invinity.com/capacity-market-auction-energy-storage/ Khan, A. S. M., Verzijlbergh, R. A., Sakinci, O. C., & De Vries, L. J. (2018). How do demand response and electrical energy storage affect (the need for) a capacity market? Applied Energy, 214(January), 39–62. https://doi.org/10.1016/j.apenergy.2018.01.057 Lamoulie, D. (2017). The French electricity capacity market. Eecc.Eu. https://www.eecc.eu/blog/the-french-electricity-capacity-market#:~:text=How the capacity market works,their clients during peak periods. Millán, J., Benavides, J., & Schutt, E. (2022). El Mercado de la Energía Eléctrica en Colombia: Características, Evolución e Impacto sobre otros Sectores. Centro de Investigación Económica y Social FEDESARROLLO, 1–304. Ministerio de Hacienda. (2024). ABECÉ. Fondo de estabilización de precios de los combustibles - FEPC. https://www.minhacienda.gov.co/webcenter/ShowProperty?nodeId=%2FConexionContent% 2FWCC_CLUSTER-192817%2F%2FidcPrimaryFile&revision=latestreleased Ministerio de Minas y Energía. (1999). Balance de la Reforma del Sector Eléctrico. Ministerio de Minas y Energía. (2023). Ley 143 de 1994. FUNCIÓNPÚBLICA.Gov.Co. Morales, A. C., Adrián, C., Flórez, C., Andrés, M., Orozco, P., Herrera, B., Paula, J., & Sánchez García, L. (2023). Proyección de precios de los energéticos para generación eléctrica julio 2023 diciembre 2050. Moreno, R., Cantillo, S. A., & Carrillo-Rodriguez, L. A. (2021). Risk analysis of firm energy coverage in Colombia in the medium term. International Journal of Energy Economics and Policy, 11(2), 220–226. https://doi.org/10.32479/ijeep.10490 Name, J. D. (2023). Verdades del cargo por confiabilidad. Portafolio. Navarro, J. C. J. (2021). Lessons from the implementation of the reliability payment mechanism in Colombia as an incentive for electricity generation. Desarrollo y Sociedad, 2021(87), 113–148. https://doi.org/10.13043/DYS.87.4 Norton Rose Fulbright. (2015). Capacity market in France. Nortonrosefulbright.Com. https://www.nortonrosefulbright.com/en/knowledge/publications/db70dcf8/capacity-market-in-france Oficina de Estudios Económicos, G. A. de R. T. (2014). Mercados de Capacidad y Confiabilidad en el Sector Eléctrico : Aspectos Conceptuales y Experiencias Internacionales. Olave, D., Álvarez, E., Rodríguez, A., & Tenreiro, C. (2017). An optimization framework for investment evaluation of complex renewable energy systems. Energies, 10(7), 1–26. https://doi.org/10.3390/en10071062 Open. (2019). ¿Cuál es el panorama actual del mercado competitivo eléctrico en Estados Unidos? Openintl.Com. https://www.openintl.com/es/mercado-competitivo-electrico-panorama-en-estados-unidos/ Ospina, A. D., & Mosquera, D. (2016). Cargo por confiabilidad: ¿éxito o fracaso? Con-Texto, 45, 13– 36. https://doi.org/10.18601/01236458.n45.03 Ospina, G. (2019). Guatapé y Playas, centrales renacidas de las “cenizas.” El Colombiano. https://www.elcolombiano.com/antioquia/guatape-y-playas-centrales-renacidas-de-las-cenizas-AG12141616 Otero, D. (2022, August 19). Los precios de los combustibles hay que desligarlos de los precios internacionales. Indepaz. Pecasting, N. (2023). Entrevista a Nicolas Pecastaing: La relación entre el cambio climático y el Fenómeno El Niño. Ciup.up.Edu.Pe. https://ciup.up.edu.pe/analisis/entrevista-a-nicolas-pecastaing-la-relacion-entre-el-cambio-climatico-y-el-fenomeno-el-nino/ Phillips, J. (2014). Electricity market reform: the Capacity Market explained. Inhouselawyer.Co.Uk. https://www.inhouselawyer.co.uk/legal-briefing/electricity-market-reform-the-capacity-market-explained / PJM. (2022). 2022/2023 RPM Base Residual Auction Results BRA Resource Clearing Prices Capacity Type Rest of RTO MAAC EMAAC BGE COMED DEOK 2022/23 BRA Resource Clearing Prices ($/MW-day). PJM. (2023a). Clearing Prices and Charges. PJM. (2023b). PJM 2022 Financial Report. PJM. (2023c). PJM Manual 18: PJM Capacity Market. 1–241. PJM. (2023d). Gas/Electric Industry Coordination. Learn.Pjm.Com. https://learn.pjm.com/three-priorities/keeping-the-lights-on/gas-electric-industry PJM. (2023e). PJM Capacity Auction Secures Electricity Supplies at Competitive Prices. Pjm.Com. https://doi.org/10.1080/0300443900570115 PJM. (2023f). PJM System Mix -System Mix By Fuel - 01/2022 to 12/2022. Gats.Pjm-Eis.Com. https://gats.pjm-eis.com/GATS2/PublicReports/PJMSystemMix/Filter PJM. (2023g). Who We Are. Pjm.Com. https://www.pjm.com/about-pjm/who-we-are RBP. (2022). ENERGY POLICY WA RESERVE CAPACITY MECHANISM REVIEW-INTERNATIONAL REVIEW. RTE. (2023a). Market mechanisms. Bilan-Electrique-2020.Rte-France.Com. https://bilan-electrique- 2020.rte-france.com/market-mechanism-capacity-mechanism/?lang=en RTE. (2023b). Participate in the capacity mechanism. Services-Rte.Com. https://www.servicesarte.com/en/learn-more-about-our-services/participate-in-the-capacity-mechanism.html RTE. (2023c). Responding to the call for tenders for new capacities. Services-Rte.Com. https://www.services-rte.com/en/learn-more-about-our-services/participate-in-the-capacity-mechanism/call-for-tenders-for-new-capacities.html Sáenz, J. (2021). La fragilidad oculta en el transporte del gas natural en Colombia. El Espectador. https://www.elespectador.com/economia/la-fragilidad-oculta-en-el-transporte-del-gas-natural-en-colombia/ Safeguard Global. (2023). Los diez principales países productores del mundo. Safeguardglobal.Com. https://www.safeguardglobal.com/es/resources/blog/los-diez-principales-paises-productores-del-mundo/ Simoglou, C. K., & Biskas, P. N. (2023). Capacity Mechanisms in Europe and the US: A Comparative Analysis and a Real-Life Application for Greece. Energies, 16(2), 32. https://doi.org/10.3390/en16020982 Statista. (2022). Electricity in France - statistics & facts. Statista.Com. https://www.statista.com/topics/8512/electricity-market-in-france/#editorsPicks Statista. (2023a). 30 países más grandes del mundo por superficie total a fecha de julio de 2022. Es.Statista.Com. https://es.statista.com/estadisticas/635141/paises-mas-grandes-del-mundo/ Statista. (2023b). Distribution of electricity generation in Australia in 2022, by source. Statista.Com. https://www.statista.com/statistics/1234850/australia-distribution-of-electricity-production-by-source/ Statista. (2023c). Distribution of electricity generation in France in 2022, by source. Statista.Com. https://www.statista.com/statistics/1235410/france-distribution-of-electricity-production-by-source/#:~:text=In 2022%2C nuclear power accounted,electricity generation%2C with 9.8 percent. Statista. (2023d). Electricity generation in the UK - statistics & facts. Statista.Com. Strategy, A. (2017). La experiencia internacional Los mercados eléctricos en otros países y su comparación con España. 1–20 Universidad de la Sabana. (2023). Petróleo, dólar y bolsa de valores: una relación de nunca acabar. Unisabana.Edu.Co. https://www.unisabana.edu.co/portaldenoticias/al-dia/petroleo-dolar-y-bolsa-de-valores-una-relacion-de-nunca-acabar/ UPME, U. de P. M. E. (2015). Capitulo 1. Hidroenergía. Atlas de Potencial Hidroenergético de Colombia, 25–36. Valencia, G. (2023). La problemática sectorial del gas natural. Pares. https://www.pares.com.co/post/la-problem%C3%A1tica-sectorial-del-gas-natural Vargas Riaño, D. A. (2022). “Colombia tiene una de las matrices de generación eléctrica más limpias del mundo”: Acolgén. El Colombiano . https://www.elcolombiano.com/negocios/que-efectos-tendra-la-guerra-entre-rusia-y-ucrani-en-colombia-para-la-industria-energetica-OC17154930 Villate, J. (2014). Evaluación de la seguridad de abastecimiento de energía en Colombia basado en el cargo por confiabilidad. Universidad de Los Andes. World Population review. (2023). Electricity Production by Country 2023. Worldpopulationreview.Com. https://worldpopulationreview.com/country-rankings/electricity-production-by-country XM. (2023a). Cargo por confiabilidad. Xm.Com.Co. https://www.xm.com.co/transacciones/cargo-por-confiabilidad/descripcion XM. (2023b). Estructura del mercado. Transacciones - Registro Agentes y Contactos. https://www.xm.com.co/ XM. (2023c). Precio de bolsa y escasez. Transacciones - Cargo Por Confiabilidad. https://www.xm.com.co/ Zapata, S. (2017). Effect on security of supply of renewable energy penetration in an electricity market: risks, opportunities, and challenges. Zapata, S., Castaneda, M., Garces, E., Franco, C. J., & Dyner, I. (2018). Assessing security of supply in a largely hydroelectricity-based system: The Colombian case. Energy, 156, 444–457. https://doi.org/10.1016/j.energy.2018.05.118 |
dc.rights.coar.fl_str_mv |
http://purl.org/coar/access_right/c_abf2 |
dc.rights.license.spa.fl_str_mv |
Reconocimiento 4.0 Internacional |
dc.rights.uri.spa.fl_str_mv |
http://creativecommons.org/licenses/by/4.0/ |
dc.rights.accessrights.spa.fl_str_mv |
info:eu-repo/semantics/openAccess |
rights_invalid_str_mv |
Reconocimiento 4.0 Internacional http://creativecommons.org/licenses/by/4.0/ http://purl.org/coar/access_right/c_abf2 |
eu_rights_str_mv |
openAccess |
dc.format.extent.spa.fl_str_mv |
76 páginas |
dc.format.mimetype.spa.fl_str_mv |
application/pdf |
dc.coverage.country.none.fl_str_mv |
Colombia |
dc.publisher.spa.fl_str_mv |
Universidad Nacional de Colombia |
dc.publisher.program.spa.fl_str_mv |
Medellín - Minas - Maestría en Ingeniería - Sistemas Energéticos |
dc.publisher.faculty.spa.fl_str_mv |
Facultad de Minas |
dc.publisher.place.spa.fl_str_mv |
Medellín, Colombia |
dc.publisher.branch.spa.fl_str_mv |
Universidad Nacional de Colombia - Sede Medellín |
institution |
Universidad Nacional de Colombia |
bitstream.url.fl_str_mv |
https://repositorio.unal.edu.co/bitstream/unal/85812/1/license.txt https://repositorio.unal.edu.co/bitstream/unal/85812/2/1128456970.2024.pdf https://repositorio.unal.edu.co/bitstream/unal/85812/3/1128456970.2024.pdf.jpg |
bitstream.checksum.fl_str_mv |
eb34b1cf90b7e1103fc9dfd26be24b4a 95130055168a8d1a4ca0abdee120ad8f 1f3094fd2d8cafb781d81edd80c80995 |
bitstream.checksumAlgorithm.fl_str_mv |
MD5 MD5 MD5 |
repository.name.fl_str_mv |
Repositorio Institucional Universidad Nacional de Colombia |
repository.mail.fl_str_mv |
repositorio_nal@unal.edu.co |
_version_ |
1814089355459821568 |
spelling |
Reconocimiento 4.0 Internacionalhttp://creativecommons.org/licenses/by/4.0/info:eu-repo/semantics/openAccesshttp://purl.org/coar/access_right/c_abf2Franco Cardona, Carlos Jaimee77c35ea37c7b92041b06767ea4b4d60Castrillon Charari, Lady Snedy45717b8744cded18f353469bf305b07b2024-03-15T15:47:26Z2024-03-15T15:47:26Z2024-12-30https://repositorio.unal.edu.co/handle/unal/85812Universidad Nacional de ColombiaRepositorio Institucional Universidad Nacional de Colombiahttps://repositorio.unal.edu.co/En todo mercado de electricidad, es fundamental poder suministrar la energía demandada por las personas y empresas, a cualquier hora y en cualquier período del año. Sin embargo, en países como Colombia cuya matriz energética está fuertemente ligada a la generación de energía hidroeléctrica hay condiciones externas como los regímenes hidrológicos que se vuelven determinantes para la generación de energía. Por tanto, surgen mecanismos como el cargo por confiabilidad, que busca garantizar la disponibilidad energética en épocas críticas al contratar obligaciones de energía firme con los generadores. A pesar de esto, en épocas climáticas críticas, el país ha estado a punto de racionar debido a que el cargo por confiabilidad no ha funcionado como se esperaba, y se han tenido que implementar otros mecanismos para asegurar atención de la demanda. Por esto, esta propuesta de trabajo final está enfocada en proponer ajustes al actual mecanismo de cargo por confiabilidad del sector eléctrico colombiano. Para lograr esto, se propone inicialmente hacer una revisión exploratoria para algunos países con relación a los mercados de capacidad, donde se recopile información más amplia acerca de su normativa, sus métodos, su funcionamiento y su financiamiento; con el fin de realizar un análisis cuantitativo y cualitativo de los datos; para entender su desarrollo y falencias, y así plantear finalmente cuáles son los ajustes necesarios para que el actual cargo por confiabilidad funcione de una manera más eficiente en el mercado eléctrico local. (Tomado de la fuente)In any electricity market, it is essential to supply the energy demanded by people and companies at any time and at any time of the year. However, in countries such as Colombia, whose energy matrix is strongly linked to hydroelectric power generation, external conditions such as hydrological regimes become determinants for power generation. Therefore, mechanisms such as the reliability charge arise, which seeks to guarantee energy availability in critical times by contracting firm energy obligations with generators. Despite this, in critical climatic periods, the country has been on the verge of rationing because the reliability charge has not worked as expected, and other mechanisms have had to be implemented to ensure that demand is met. Therefore, this final work proposal is focused on proposing adjustments to the current reliability charge mechanism of the Colombian electricity sector. To achieve this, it is initially proposed to make an exploratory review of some countries with capacity markets, where more extensive information is collected about their regulations, methods, operation, and financing; to perform a quantitative and qualitative analysis of the data; to understand its development and its shortcomings, and thus finally propose what adjustments are necessary for the current reliability charge to work more efficiently in the local electricity market.Contiene tablas, ilustraciones, figurasContains tables, illustrations, figuresMaestríaMagíster en Ingeniería - Sistemas EnergéticosIngeniería De Sistemas E Informática.Sede Medellín76 páginasapplication/pdfspaUniversidad Nacional de ColombiaMedellín - Minas - Maestría en Ingeniería - Sistemas EnergéticosFacultad de MinasMedellín, ColombiaUniversidad Nacional de Colombia - Sede Medellín620 - Ingeniería y operaciones afines330 - Economía::333 - Economía de la tierra y de la energíaEnergía eléctrica - ColombiaSector energético - ColombiaDemanda de energía - ColombiaConsumo de energía - ColombiaCapacitanciaRecursos energéticos - ColombiaAbastecimiento de energía - ColombiaEconomía de la energía - ColombiaCargo por confiabilidadMercado de capacidadSector eléctricoMatriz energéticaSuministroReliability chargeCapacity marketElectricity sectorEnergy matrixSupplyAjustes al mecanismo de cargo por confiabilidad del sector eléctrico colombianoAdjustments to the reliability charge mechanism in the Colombian electricity sectorTrabajo de grado - Maestríainfo:eu-repo/semantics/masterThesisinfo:eu-repo/semantics/acceptedVersionTexthttp://purl.org/redcol/resource_type/TMColombiaLaReferenciaAEMO. (2023a). Wholesale Electricity Market Design Summary.AEMO. (2023b). About the Wholesale Electricity Market (WEM). Aemo.Com.Au. https://aemo.com.au/energy-systems/electricity/wholesale-electricity-market-wem/about the-wholesale-electricity-market-wa-wemAEMO. (2023c). Reserve Capacity Price. Aemo.Com.Au. https://aemo.com.au/energy systems/electricity/wholesale-electricity-market-wem/wa-reserve-capacity mechanism/reserve-capacity-price#:~:text=The administrative Reserve Capacity Price,set in the WEM Rules.AEMO. (2023d). Reserve Capacity Price. Aemo.Com.Au. https://aemo.com.au/energy systems/electricity/wholesale-electricity-market-wem/wa-reserve-capacity mechanism/reserve-capacity-price#:~:text=The administrative Reserve Capacity Price,set in the WEM Rules.AEMO. (2023e). Wholesale Electricity Market (WEM). Aemo.Com.Au. https://aemo.com.au/energy-systems/electricity/wholesale-electricity-market-wemANDEG. (2017). Un segundo análisis del precio de escasez.Andrés, O., Morales, C., Andrés, J., Gil, M., De, G., Upme, G., Beleño, L. A. H., Aldana, A., Henry, U., Zapata, J., Segura López, A., Fernando, C., Franco, V., Hernando, M., Ruiz, M., Tobías, F., & Cañón, O. (2023). Plan Indicativo de Expansión de la Generación.Anuta, O. H., Taylor, P., Jones, D., McEntee, T., & Wade, N. (2014). An international review of the implications of regulatory and electricity market structures on the emergence of grid scale electricity storage. Renewable and Sustainable Energy Reviews, 38, 489–508. https://doi.org/10.1016/j.rser.2014.06.006Arango, S., López, J. A., Medina, G., Domínguez, E., Uribe, E., Zapata, W., Martínez, J. F., & Correa, C. (2013). Estudio para determinar la vulnerabilidad y las opciones de adaptación del sector energético colombiano frente al cambio climáticoArango, S., Restrepo, M. I., & Vélez, L. G. (2011). La confiabilidad en los sistemas eléctricos competitivos y el modelo colombiano de cargo por confiabilidad. Cuadernos de Economía, 31(56), 199–223.Asmar, S. (2022, September 15). Diversificar la matriz y cuidado del planeta, hacia una transición energética justa y sostenible. Larepublica.Co/.Australian Government. (2023). National Electricity Market. Energy.Gov.Au. https://www.energy.gov.au/government-priorities/energy-markets/national-electricity market-nemBedoya, J. C., Rodas, E. A., & García, D. F. (2016). Descripción de los Aspectos Comerciales del Esquema del Cargo por Confiabilidad en el Mercado Eléctrico Colombiano. Scientia et Technica , 21(1), 5–14.Bell, P. L. (2012). Geografia, Topografia y Clima Colombia. Colombia : Manual Comercial e Industrial, 37–50.Bersano, L., & Paredes, J. R. (2017). En Colombia, el fenómeno del Niño, nos pone a prueba. Blogs.Iadb.Org. https://blogs.iadb.org/energia/es/2406/Bloomberg. (2023, June 16). El gas, el “salvavidas” de Venezuela para reactivar su economía. Portafolio.Brigard Urrutia. (2023). CREG define fecha de asignación para el Cargo por Confiabilidad. Bu.Com.Co. https://www.bu.com.co/es/insights/noticias/creg-define-fecha-de-asignacion para-el-cargo-por-confiabilidadCarabott, M., & Wallington, B. (2022). WA capacity charges – What are they, and how can they reduce my electricity bill. Leadingedgeenergy.Com.Au. https://www.leadingedgeenergy.com.au/blog/wa-capacity-charges/Cárdena, T. (2017). El Niño, la crisis energética y las lecciones que se aprendieron. El Eafitense. https://www.eafit.edu.co/medios/eleafitense/110/Paginas/el-nino-crisis-energetica.aspxCelsia Energía. (2021). Documento de trabajo sobre el Sistema Interconectado Nacional, SIN. 1–4.Chacón, M. (2023, November 6). Fenómeno de El Niño inicia oficialmente: su mayor intensidad empezaría desde noviembre. El Tiempo. https://www.eltiempo.com/vida/medio ambiente/fenomeno-de-el-nino-inicia-oficialmente-su-mayor-intensidad-empezaria-desde noviembre-823093#:~:text=Mateo%20Chac%C3%B3n%20Orduz- ,06%20de%20noviembre%202023%2C%2012%3A00%20A.,M.&text=El%20Instituto%20de%2 0Hidrolog%C3%ADa%2C%20Meteorolog%C3%ADa,t%C3%A9cnicos%20para%20esta%20decl aratoria%20oficial.Chestney, N. (2022, February 16). UK electricity capacity auction clears at highest ever price. Reuters. https://www.reuters.com/world/uk/uk-electricity-capacity-auction-clears-highest ever-price-2022-02-16/CNN Español. (2022). ¿Por qué el dólar estadounidense es la principal moneda del mundo? Cnnespanol.Cnn.Com. https://cnnespanol.cnn.com/2022/08/08/por-que-el-dolar estadounidense-es-la-principal-moneda-del-mundo-orixComisión de Regulación de Energía y Gas. (1996). Cargo por capacidad.Comisión de Regulación de Energía y Gas. (2007). Resolución No.071 ( 03 ct. 2006 ). http://apolo.creg.gov.co/Publicac.nsf/1c09d18d2d5ffb5b05256eee00709c02/243937481e51 77820525785a007a6f75?OpenDocument#:~:text=Cargo por Confiabilidad%3A Remuneración que,Subasta para la Asignación deComisión de Regulación de Energía y Gas. (2016). ALTERNATIVAS PARA DEFINIR EL PRECIO DE ESCASEZ.Comisión de Regulación de Energía y Gas. (2023a). Energía firme para el cargo por confiabilidad (enficc). https://www.creg.gov.co/Comisión de Regulación de Energía y Gas. (2023b). Historia en Colombia. CREG.Gov.Co.Consulting, C. (2020). Capacity markets and energy-only markets-a survey of recent developments. February, 46Contraloría General de la República. (2016b). Informe de resultados de la actuacion especial de fiscalización sobre el manejo de recursos del cargo por confiabilidad. 1, 1–57. https://observatoriofiscal.contraloria.gov.co/Publicaciones/El Manejo de Recursos del Cargo por Confiabilidad.pdfContreras, D. (2016). El impacto de El Niño en Colombia. Fasecolda, 42–46.Cour des Comptes. (2022). Organisation of the Electricity Markets (Issue July).Cramton, P., & Ockenfels, A. (2012). Economics and Design of Capacity Markets for the Power Sector. Zeitschrift Für Energiewirtschaft, 36(2), 113–134. https://doi.org/10.1007/s12398- 012-0084-2CREG. (2006a). Cargo por Confiabilidad. 87.CREG. (2006b). Cargo por Confiabilidad. 87. http://www.xm.com.co/Promocin Primera Subasta de Energa Firme/abc2.pdfCREG. (2024). Compilación del Cargo por Confiabilidad en el Mercado Mayorista de Energía Eléctrica. https://gestornormativo.creg.gov.co/gestor/entorno/docs/ru_creg_cc.htmDahiru, A. T., Daud, D., Tan, C. W., Jagun, Z. T., Samsudin, S., & Dobi, A. M. (2023). A comprehensive review of demand side management in distributed grids based on real estate perspectives. Environmental Science and Pollution Research. https://doi.org/10.1007/s11356-023-25146-xDatosmacros.com. (2023). Población. Datosmacro.Expansion.Com. https://datosmacro.expansion.com/demografia/poblacionDuque, J. P. B., García, J. J., & Velásquez, H. (2016). Efectos del cargo por confiabilidad sobre el precio spot de la energía eléctrica en colombia. Cuadernos de Economia (Colombia), 35(68), 491–519. https://doi.org/10.15446/cuad.econ.v35n68.52732Dyner, I., Franco, C. J., Cadavid, L., García, A., Giraldo, E. A., Giraldo, J. E., Gómez, D. F., Nieto, M. J., Rodríguez, R., & Quiceno, G. (2018). Ocaso de un paradigma. Hacia un nuevo modelo eléctrico (I. Dyner & C. J. Franco, Eds.; Primera). Fondo de Cultura Económica, Universidad de Bogotá Jorge Tadeo Lozano.EIA. (2023). Electricity in the United States. U.S. Energy Information Administration. https://www.eia.gov/energyexplained/electricity/electricity-in-the-us.phpEl Heraldo. (2016). “Daño en Termoflores aumenta riesgo de apagón”: Andeg. El Heraldo.Enel. (2023). Descripción del Mercado. Así Llega La Energía y El Gas a Tu Empresa. https://www.enel.com.co/es/empresas/enel-generacion/como-se-genera-la-electricidad.htmlEnerdata. (2023a). Producción de electricidad. Enerdata. https://datos.enerdata.net/electricidad/estadisticas-mundiales-produccion-electricidad.htmlEnerdata. (2023b). Producción de gas natural. Datos.Enerdata.Net. https://datos.enerdata.net/gas-natural/produccion-gas-natural-mundial.htmlEnergy UK. (2023). Electricity generation. Energy-Uk.Org.Uk. https://www.energy uk.org.uk/insights/electricity-generation/EPA. (2023a). Power Market Structure. Epa.Gov. https://www.epa.gov/green-power markets/power-market-structureEPA. (2023b). The U.S. Electricity System. About the U.S. Electricity System and Its Impact on the Environment. https://www.epa.gov/energy/about-us-electricity-system-and-its-impact environment#:~:text=Electricity in the United States,generated at centralized power plants.Estrada, M. P., Duque, B. M., & Rendón, J. J. (2017). Análisis comparativo de diferentes esquemas de suficiencia en generación eléctrica: Algunas reflexiones para el mercado eléctrico en Colombia. Energy, 16, 1–33.Flexcity. (2021a). Increase in the prices of the French Capacity Mechanism auction. Flexcity.Energy. https://www.flexcity.energy/it/increase-the-prices-of-the-french-capacity-mechanism auctionFlexcity. (2021b). Increase in the prices of the French Capacity Mechanism auction. Flexcity.Energy. https://www.flexcity.energy/it/increase-the-prices-of-the-french-capacity-mechanism-auctionFlexitricity. (2023). Capacity Market. Flexitricity.Com. https://flexitricity.com/services/capacity-market/#:~:text=The Capacity Market (CM) was,System Stress Event could occur.Franco, C. J. (2023). Los Mercados Mayoristas de Electricidad Estructura y Comercialización (pp. 1– 26).Fundación Endesa. (2023a). Central térmica convencional. https://www.fundacionendesa.org/Garcés, E. (2013). Evaluación de políticas para garantizar el abastecimiento de energía eléctrica en Colombia.García, L. F. (2023, April 19). Plenaria aprueba prohibición del fracking en Colombia. Senado.Gov.Co. https://www.senado.gov.co/index.php/el-senado/noticias/4468-plenaria aprueba-prohibicion-del-fracking-en-colombiaGeoscience Australia. (2023). Overviw. Ga.Gov.Au. https://www.ga.gov.au/scientific-topics/energy/overviewGrupo Banco Mundial. (2023). Población total. Banco Mundial. https://datos.bancomundial.org/indicator/SP.POP.TOTL?most_recent_value_desc=trueHeaton, A. (2022). Chapter 4: Natural Gas Chart 4.1 Supply and demand for natural. https://assets.publishing.service.gov.uk/Howorth, N., Pay, J., Shepherd, J., & Coxall, M. (2015). Capacity Market: an EMR Primer. https://www.cliffordchance.com/Hurtado, J. I. (2014). Cronología del sector eléctrico colombiano. Revista de Santander, 9, 22.Ideam. (2023). Fenómenos del Niño y la Niña. Ministerio de Ambiente y Desarrollo Sostenible de Colombia. http://www.ideam.gov.co/web/siac/ninoyninaIEA. (2023a). Australia. Iea.Org. https://www.iea.org/countries/australiaIEA. (2023b). France. Iea.Org. https://www.iea.org/countries/franceIEA. (2023c). United Kingdom. Iea.Org. https://www.iea.org/countries/united-kingdomInstitute for Government. (2022). Electricity market. Instituteforgovernment.Org.Uk. https://www.instituteforgovernment.org.uk/article/explainer/electricity-marketInvinity Energy Systems. (2023). What the 2022 T-1 Capacity Market Auction Tells Us About Wholesale Market Prices for Energy Storage. Invinity.Com. https://invinity.com/capacity-market-auction-energy-storage/Khan, A. S. M., Verzijlbergh, R. A., Sakinci, O. C., & De Vries, L. J. (2018). How do demand response and electrical energy storage affect (the need for) a capacity market? Applied Energy, 214(January), 39–62. https://doi.org/10.1016/j.apenergy.2018.01.057Lamoulie, D. (2017). The French electricity capacity market. Eecc.Eu. https://www.eecc.eu/blog/the-french-electricity-capacity-market#:~:text=How the capacity market works,their clients during peak periods.Millán, J., Benavides, J., & Schutt, E. (2022). El Mercado de la Energía Eléctrica en Colombia: Características, Evolución e Impacto sobre otros Sectores. Centro de Investigación Económica y Social FEDESARROLLO, 1–304.Ministerio de Hacienda. (2024). ABECÉ. Fondo de estabilización de precios de los combustibles - FEPC. https://www.minhacienda.gov.co/webcenter/ShowProperty?nodeId=%2FConexionContent% 2FWCC_CLUSTER-192817%2F%2FidcPrimaryFile&revision=latestreleasedMinisterio de Minas y Energía. (1999). Balance de la Reforma del Sector Eléctrico.Ministerio de Minas y Energía. (2023). Ley 143 de 1994. FUNCIÓNPÚBLICA.Gov.Co.Morales, A. C., Adrián, C., Flórez, C., Andrés, M., Orozco, P., Herrera, B., Paula, J., & Sánchez García, L. (2023). Proyección de precios de los energéticos para generación eléctrica julio 2023 diciembre 2050.Moreno, R., Cantillo, S. A., & Carrillo-Rodriguez, L. A. (2021). Risk analysis of firm energy coverage in Colombia in the medium term. International Journal of Energy Economics and Policy, 11(2), 220–226. https://doi.org/10.32479/ijeep.10490Name, J. D. (2023). Verdades del cargo por confiabilidad. Portafolio.Navarro, J. C. J. (2021). Lessons from the implementation of the reliability payment mechanism in Colombia as an incentive for electricity generation. Desarrollo y Sociedad, 2021(87), 113–148. https://doi.org/10.13043/DYS.87.4Norton Rose Fulbright. (2015). Capacity market in France. Nortonrosefulbright.Com. https://www.nortonrosefulbright.com/en/knowledge/publications/db70dcf8/capacity-market-in-franceOficina de Estudios Económicos, G. A. de R. T. (2014). Mercados de Capacidad y Confiabilidad en el Sector Eléctrico : Aspectos Conceptuales y Experiencias Internacionales.Olave, D., Álvarez, E., Rodríguez, A., & Tenreiro, C. (2017). An optimization framework for investment evaluation of complex renewable energy systems. Energies, 10(7), 1–26. https://doi.org/10.3390/en10071062Open. (2019). ¿Cuál es el panorama actual del mercado competitivo eléctrico en Estados Unidos? Openintl.Com. https://www.openintl.com/es/mercado-competitivo-electrico-panorama-en-estados-unidos/Ospina, A. D., & Mosquera, D. (2016). Cargo por confiabilidad: ¿éxito o fracaso? Con-Texto, 45, 13– 36. https://doi.org/10.18601/01236458.n45.03Ospina, G. (2019). Guatapé y Playas, centrales renacidas de las “cenizas.” El Colombiano. https://www.elcolombiano.com/antioquia/guatape-y-playas-centrales-renacidas-de-las-cenizas-AG12141616Otero, D. (2022, August 19). Los precios de los combustibles hay que desligarlos de los precios internacionales. Indepaz.Pecasting, N. (2023). Entrevista a Nicolas Pecastaing: La relación entre el cambio climático y el Fenómeno El Niño. Ciup.up.Edu.Pe. https://ciup.up.edu.pe/analisis/entrevista-a-nicolas-pecastaing-la-relacion-entre-el-cambio-climatico-y-el-fenomeno-el-nino/Phillips, J. (2014). Electricity market reform: the Capacity Market explained. Inhouselawyer.Co.Uk. https://www.inhouselawyer.co.uk/legal-briefing/electricity-market-reform-the-capacity-market-explained
/PJM. (2022). 2022/2023 RPM Base Residual Auction Results BRA Resource Clearing Prices Capacity Type Rest of RTO MAAC EMAAC BGE COMED DEOK 2022/23 BRA Resource Clearing Prices ($/MW-day).PJM. (2023a). Clearing Prices and Charges.PJM. (2023b). PJM 2022 Financial Report.PJM. (2023c). PJM Manual 18: PJM Capacity Market. 1–241.PJM. (2023d). Gas/Electric Industry Coordination. Learn.Pjm.Com. https://learn.pjm.com/three-priorities/keeping-the-lights-on/gas-electric-industryPJM. (2023e). PJM Capacity Auction Secures Electricity Supplies at Competitive Prices. Pjm.Com. https://doi.org/10.1080/0300443900570115PJM. (2023f). PJM System Mix -System Mix By Fuel - 01/2022 to 12/2022. Gats.Pjm-Eis.Com. https://gats.pjm-eis.com/GATS2/PublicReports/PJMSystemMix/FilterPJM. (2023g). Who We Are. Pjm.Com. https://www.pjm.com/about-pjm/who-we-areRBP. (2022). ENERGY POLICY WA RESERVE CAPACITY MECHANISM REVIEW-INTERNATIONAL REVIEW.RTE. (2023a). Market mechanisms. Bilan-Electrique-2020.Rte-France.Com. https://bilan-electrique- 2020.rte-france.com/market-mechanism-capacity-mechanism/?lang=enRTE. (2023b). Participate in the capacity mechanism. Services-Rte.Com. https://www.servicesarte.com/en/learn-more-about-our-services/participate-in-the-capacity-mechanism.htmlRTE. (2023c). Responding to the call for tenders for new capacities. Services-Rte.Com. https://www.services-rte.com/en/learn-more-about-our-services/participate-in-the-capacity-mechanism/call-for-tenders-for-new-capacities.htmlSáenz, J. (2021). La fragilidad oculta en el transporte del gas natural en Colombia. El Espectador. https://www.elespectador.com/economia/la-fragilidad-oculta-en-el-transporte-del-gas-natural-en-colombia/Safeguard Global. (2023). Los diez principales países productores del mundo. Safeguardglobal.Com. https://www.safeguardglobal.com/es/resources/blog/los-diez-principales-paises-productores-del-mundo/Simoglou, C. K., & Biskas, P. N. (2023). Capacity Mechanisms in Europe and the US: A Comparative Analysis and a Real-Life Application for Greece. Energies, 16(2), 32. https://doi.org/10.3390/en16020982Statista. (2022). Electricity in France - statistics & facts. Statista.Com. https://www.statista.com/topics/8512/electricity-market-in-france/#editorsPicksStatista. (2023a). 30 países más grandes del mundo por superficie total a fecha de julio de 2022. Es.Statista.Com. https://es.statista.com/estadisticas/635141/paises-mas-grandes-del-mundo/Statista. (2023b). Distribution of electricity generation in Australia in 2022, by source. Statista.Com. https://www.statista.com/statistics/1234850/australia-distribution-of-electricity-production-by-source/Statista. (2023c). Distribution of electricity generation in France in 2022, by source. Statista.Com. https://www.statista.com/statistics/1235410/france-distribution-of-electricity-production-by-source/#:~:text=In 2022%2C nuclear power accounted,electricity generation%2C with 9.8 percent.Statista. (2023d). Electricity generation in the UK - statistics & facts. Statista.Com.Strategy, A. (2017). La experiencia internacional Los mercados eléctricos en otros países y su comparación con España. 1–20Universidad de la Sabana. (2023). Petróleo, dólar y bolsa de valores: una relación de nunca acabar. Unisabana.Edu.Co. https://www.unisabana.edu.co/portaldenoticias/al-dia/petroleo-dolar-y-bolsa-de-valores-una-relacion-de-nunca-acabar/UPME, U. de P. M. E. (2015). Capitulo 1. Hidroenergía. Atlas de Potencial Hidroenergético de Colombia, 25–36.Valencia, G. (2023). La problemática sectorial del gas natural. Pares. https://www.pares.com.co/post/la-problem%C3%A1tica-sectorial-del-gas-naturalVargas Riaño, D. A. (2022). “Colombia tiene una de las matrices de generación eléctrica más limpias del mundo”: Acolgén. El Colombiano . https://www.elcolombiano.com/negocios/que-efectos-tendra-la-guerra-entre-rusia-y-ucrani-en-colombia-para-la-industria-energetica-OC17154930Villate, J. (2014). Evaluación de la seguridad de abastecimiento de energía en Colombia basado en el cargo por confiabilidad. Universidad de Los Andes.World Population review. (2023). Electricity Production by Country 2023. Worldpopulationreview.Com. https://worldpopulationreview.com/country-rankings/electricity-production-by-countryXM. (2023a). Cargo por confiabilidad. Xm.Com.Co. https://www.xm.com.co/transacciones/cargo-por-confiabilidad/descripcionXM. (2023b). Estructura del mercado. Transacciones - Registro Agentes y Contactos. https://www.xm.com.co/XM. (2023c). Precio de bolsa y escasez. Transacciones - Cargo Por Confiabilidad. https://www.xm.com.co/Zapata, S. (2017). Effect on security of supply of renewable energy penetration in an electricity market: risks, opportunities, and challenges.Zapata, S., Castaneda, M., Garces, E., Franco, C. J., & Dyner, I. (2018). Assessing security of supply in a largely hydroelectricity-based system: The Colombian case. Energy, 156, 444–457. https://doi.org/10.1016/j.energy.2018.05.118EstudiantesInvestigadoresMaestrosResponsables políticosLICENSElicense.txtlicense.txttext/plain; charset=utf-85879https://repositorio.unal.edu.co/bitstream/unal/85812/1/license.txteb34b1cf90b7e1103fc9dfd26be24b4aMD51ORIGINAL1128456970.2024.pdf1128456970.2024.pdfTrabajo de grado de Maestría en Sistemas Energéticosapplication/pdf858206https://repositorio.unal.edu.co/bitstream/unal/85812/2/1128456970.2024.pdf95130055168a8d1a4ca0abdee120ad8fMD52THUMBNAIL1128456970.2024.pdf.jpg1128456970.2024.pdf.jpgGenerated Thumbnailimage/jpeg5393https://repositorio.unal.edu.co/bitstream/unal/85812/3/1128456970.2024.pdf.jpg1f3094fd2d8cafb781d81edd80c80995MD53unal/85812oai:repositorio.unal.edu.co:unal/858122024-08-23 23:11:25.735Repositorio Institucional Universidad Nacional de Colombiarepositorio_nal@unal.edu.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 |