Propuesta e implementación de un modelo de planeación, programación y control de la producción en una empresa fabricante de productos para el sector eléctrico
This paper proposes to model of planning, programming and control production to one company that make products for the electric sector under a productive environment Job Shop - Make To Order, this company in the last year, in the months on August, September and October fail in fulfillment 70% of ord...
- Autores:
-
Ramírez Jiménez, Carlos Alberto
Espinosa Valencia, Yerson Alberto
- Tipo de recurso:
- Fecha de publicación:
- 2019
- Institución:
- Universidad de San Buenaventura
- Repositorio:
- Repositorio USB
- Idioma:
- spa
- OAI Identifier:
- oai:bibliotecadigital.usb.edu.co:10819/6938
- Acceso en línea:
- http://hdl.handle.net/10819/6938
- Palabra clave:
- Planeación de la producción
Plan maestro de la producción
Planeación de recursos de manufactura
Planeación de ventas y operaciones
Producción bajo pedido
Job shop
Secuencia de operaciones
Control de la producción
Control de planta
Reglas de secuenciación
PLLPS
TPC
Production planning
Production master plan
Planning of manufacturing resources
Sales planning and operations
On-demand manufacturing
Workshop
Order fulfillment
Operations sequencing
Production control
Sequencing rules
FIFO
SPT
Mejoramiento de procesos
Planeación estratégica
Control de la producción
- Rights
- License
- Atribución-NoComercial-SinDerivadas 2.5 Colombia
id |
SANBUENAV2_f7f9a18be2a93103d3fdd66b0a5100fa |
---|---|
oai_identifier_str |
oai:bibliotecadigital.usb.edu.co:10819/6938 |
network_acronym_str |
SANBUENAV2 |
network_name_str |
Repositorio USB |
repository_id_str |
|
dc.title.spa.fl_str_mv |
Propuesta e implementación de un modelo de planeación, programación y control de la producción en una empresa fabricante de productos para el sector eléctrico |
title |
Propuesta e implementación de un modelo de planeación, programación y control de la producción en una empresa fabricante de productos para el sector eléctrico |
spellingShingle |
Propuesta e implementación de un modelo de planeación, programación y control de la producción en una empresa fabricante de productos para el sector eléctrico Planeación de la producción Plan maestro de la producción Planeación de recursos de manufactura Planeación de ventas y operaciones Producción bajo pedido Job shop Secuencia de operaciones Control de la producción Control de planta Reglas de secuenciación PLLPS TPC Production planning Production master plan Planning of manufacturing resources Sales planning and operations On-demand manufacturing Workshop Order fulfillment Operations sequencing Production control Sequencing rules FIFO SPT Mejoramiento de procesos Planeación estratégica Control de la producción |
title_short |
Propuesta e implementación de un modelo de planeación, programación y control de la producción en una empresa fabricante de productos para el sector eléctrico |
title_full |
Propuesta e implementación de un modelo de planeación, programación y control de la producción en una empresa fabricante de productos para el sector eléctrico |
title_fullStr |
Propuesta e implementación de un modelo de planeación, programación y control de la producción en una empresa fabricante de productos para el sector eléctrico |
title_full_unstemmed |
Propuesta e implementación de un modelo de planeación, programación y control de la producción en una empresa fabricante de productos para el sector eléctrico |
title_sort |
Propuesta e implementación de un modelo de planeación, programación y control de la producción en una empresa fabricante de productos para el sector eléctrico |
dc.creator.fl_str_mv |
Ramírez Jiménez, Carlos Alberto Espinosa Valencia, Yerson Alberto |
dc.contributor.advisor.none.fl_str_mv |
Ayora Piedrahita, Claudia Ximena |
dc.contributor.author.none.fl_str_mv |
Ramírez Jiménez, Carlos Alberto Espinosa Valencia, Yerson Alberto |
dc.subject.spa.fl_str_mv |
Planeación de la producción Plan maestro de la producción Planeación de recursos de manufactura Planeación de ventas y operaciones Producción bajo pedido Job shop Secuencia de operaciones Control de la producción Control de planta Reglas de secuenciación PLLPS TPC Production planning Production master plan Planning of manufacturing resources Sales planning and operations On-demand manufacturing Workshop Order fulfillment Operations sequencing Production control Sequencing rules FIFO SPT |
topic |
Planeación de la producción Plan maestro de la producción Planeación de recursos de manufactura Planeación de ventas y operaciones Producción bajo pedido Job shop Secuencia de operaciones Control de la producción Control de planta Reglas de secuenciación PLLPS TPC Production planning Production master plan Planning of manufacturing resources Sales planning and operations On-demand manufacturing Workshop Order fulfillment Operations sequencing Production control Sequencing rules FIFO SPT Mejoramiento de procesos Planeación estratégica Control de la producción |
dc.subject.lemb.spa.fl_str_mv |
Mejoramiento de procesos Planeación estratégica Control de la producción |
description |
This paper proposes to model of planning, programming and control production to one company that make products for the electric sector under a productive environment Job Shop - Make To Order, this company in the last year, in the months on August, September and October fail in fulfillment 70% of orders, with an average delay of 12 business days according to the delivery date agreed with the customers. An causes analysis is carried out and weaknesses have been identified in the planning, programming and control of operations in the production processes for current half and voltage transformers, a model is presented for the elaboration of a plan of production, a master production plan (MPS), material requirements plan (MRP) and a production program validated by means of a selection design for two sequencing rules based on the objectives set, using the scoring methodology is rated as performance indicator the Average Work Delay (RPT) , and the rule First in Arriving First in Service (PLLPS) is selected, finally it is validated in the implementation that the fulfillment of the orders improved by 43% and was reduced the average delay of works to 0 days. |
publishDate |
2019 |
dc.date.accessioned.none.fl_str_mv |
2019-02-22T15:44:52Z |
dc.date.available.none.fl_str_mv |
2019-02-22T15:44:52Z |
dc.date.issued.none.fl_str_mv |
2019 |
dc.date.submitted.none.fl_str_mv |
2019-02-22 |
dc.type.spa.fl_str_mv |
Trabajo de grado - Pregrado |
dc.type.coar.fl_str_mv |
http://purl.org/coar/resource_type/c_7a1f |
dc.type.spa.spa.fl_str_mv |
Trabajo de Grado |
dc.type.driver.spa.fl_str_mv |
info:eu-repo/semantics/bachelorThesis |
dc.identifier.uri.none.fl_str_mv |
http://hdl.handle.net/10819/6938 |
url |
http://hdl.handle.net/10819/6938 |
dc.language.iso.spa.fl_str_mv |
spa |
language |
spa |
dc.rights.coar.fl_str_mv |
http://purl.org/coar/access_right/c_abf2 |
dc.rights.cc.spa.fl_str_mv |
Atribución-NoComercial-SinDerivadas 2.5 Colombia |
dc.rights.uri.spa.fl_str_mv |
http://creativecommons.org/licenses/by-nc-nd/2.5/co/ |
rights_invalid_str_mv |
Atribución-NoComercial-SinDerivadas 2.5 Colombia http://creativecommons.org/licenses/by-nc-nd/2.5/co/ http://purl.org/coar/access_right/c_abf2 |
dc.format.spa.fl_str_mv |
pdf |
dc.format.extent.spa.fl_str_mv |
131 páginas: ilustraciones |
dc.format.medium.spa.fl_str_mv |
Recurso en linea |
dc.format.mimetype.spa.fl_str_mv |
application/pdf |
dc.publisher.spa.fl_str_mv |
Universidad de San Buenaventura, Cali |
dc.publisher.faculty.spa.fl_str_mv |
Ingenierias |
dc.publisher.program.spa.fl_str_mv |
Ingeniería Industrial |
dc.publisher.sede.spa.fl_str_mv |
Cali |
institution |
Universidad de San Buenaventura |
dc.source.bibliographicCitation.spa.fl_str_mv |
[1] Comercio Exterior - DINERO, «DINERO,» 22 2 2018. [En línea]. Available: http://www.dinero.com/economia/articulo/28-anos-apertura-economica/255671. [Último acceso: 13 3 2018]. [2] Grupo de Investigación en nuevas tecnologias , «Modelo de Planeación - Documento en Curso,» Programa de Ing. Industrial, Cali , 2017. [3] F. Perzella, G. Morganti. y G. Ciaschetti, «A genetic algorithm for the Flexible Job-shop Scheduling Problem,» Computers & Operations Research, vol. 35, pp. 3202 - 3212, 2008. [4] RITZ, «RITZ Instrument Transformers,» 16 Noviembre 2017. [En línea]. Available: http://ritz-international.com/language/es/productos/1365-2/. [Último acceso: 26 01 2018]. [5] J. A. M. Idarraga, «Propuesta para implementar un sistemas de programacionde la produccion,bajo teoria de restricciones, en una empresa de artes graficas.,» Universidad de Antioquia, Medellin, 2006. [6] C. R. d. l. R. Navas, «Planeación y control del proceso de producción de vigueta y poste pretensado de la empresa precon,» Universidad de San Carlos de Guatemala, Guatemala, 2015. [7] A. V. Pereira, «Análisis y desarrollo del sistema de planeación y control de la producción en una empresa de confecciones,» Cali, 2013. [8] A. Hees, C. Bayerl, B. V. Vuuren, C. S. Schutte, S. Braunreuther y G. Reinhart, «A production planning method to optimally exploit the potential of reconfigurable manufacturing systems,» Procedia CIRP, pp. 181-185, 2017. [9] R. J. Sampaio, R. R.G.Wollmann y P. F.G.Vieira, «A flexible production planning for rolling-horizons,» Int. J. Production Economics, pp. 31-36, 2017. [10] S. H. Kim y Y. H. Lee, «Synchronized production planning and scheduling in semiconductor fabrication,» Computers & Industrial Engineering, pp. 72-84, 2016. [11] A. T. ,. V. V. Carlos Herrera, «Simulation of a Hybrid Product-Driven System for Manufacturing Planning and Control,» IFAC Proceedings Volumes, pp. 69-73, 2013. [12] K. Y.P.Martínez, E. A.V.Toso y ReinaldoMorabito, «Production planning in the molded pulp packaging industry,» Computers & Industrial Engineering, pp. 554-566, 2016. [13] L. Shen, S. Dauzere y J. S, «Solving the flexible job shop scheduling problem with sequence-dependent setup times,» European Journal of Operational Research, vol. 265, pp. 503 - 516, 2018. [14] N. Kundakcı y O. Kulak, «Hybrid genetic algorithms for minimizing makespan in dynamic job shop scheduling problem,» Computers & Industrial Engineering, vol. 96, pp. 31-51, 2016. [15] K. Zhou Gao, P. Nagaratnam Suganthan, T. Jin Chua y C. Soon Chong, «A two-stage artificial bee colony algorithm scheduling flexible job-shop scheduling problem with new job insertion,» Expert Systems with Applications, vol. 42, pp. 7652 - 7663, 2015. [16] Z. Z. Mengna Hong, Y. Man, J. L. Yanzhong Zhang y H. Liu, «Multi-object optimization of flexible flow shop scheduling with batch process — Consideration total electricity consumption and material wastage,» Journal of Cleaner Production, vol. 183, pp. 925 - 939, 2018. [17] B. Shi, X. Qian, S. Sun y L. Yan, «Rule-based scheduling of multi-stage multi-product batch plants with parallel units,» Chinese Journal of Chemical Engineering, vol. 25, pp. 1022 - 1036, 2017. [18] E. G. Birgina, J. E. Ferreirab y D. P. Ronconib, «List scheduling and beam search methods for the flexible job shop scheduling problem with sequencing flexibility,» European Journal of Operational Research, vol. 247, pp. 4021-4040, 2015. [19] U. Golle , N. Boysen y F. Rothlauf, «Analysis and design of sequencing rules for car sequencing,» European Journal of Operational Research , vol. 206, p. 579–585, 2010. [20] R. Romero Silva , S. Shaaban, E. Marsillac y M. Hurtado , «Exploiting the characteristics of serial queues to reduce the mean and variance of flow time using combined priority rules,» International Journal of Production Economics , vol. 196 , p. 211–225, 2018. [21] 16 Noviembre 2017. [En línea]. Available: https://atelelectric.com/aisladores/. [Último acceso: 26 01 2018]. [22] C. J. B. Pérez, Producción y operaciones aplicadas a las pyme, ECOE EDICIONES, 2015. [23] J. G. Babon y L. C. Arbos, Gestion integral de la calidad (5ta Edicion), Barcelona: PROFIT, 2017. [24] R. A. Rojas Medina, «Contabilidad de costos,» de Contabilidad de costos un enfoque administrativo y de Gerencia, Manizales, ( No publicado), 2014, pp. 1-8. [25] S. Song, KannanGovindan, L. Xu, P. Du y X. Qiao, «Capacity and production planning with carbon emission constraints,» Transportation Research Part E, pp. 1-2, 2017. [26] HuataoPeng y YangLiu, «A comprehensive analysis of cleaner production policies in China,» Journal of Cleaner Production, pp. 1-3, 2016. [27] Sin-HoonHum, MahmutParlar y YunZhou, «Measurement and optimization of responsiveness in supply chain networks with queueing structures,» European Journal of Operational Research, pp. 106-107, 2018. [28] M. P. M. Vázquez y M. J. M. Ruíz, «Elementos que Afectan el Nivel de Inventario en Proceso (WIP) y los Costos de una Línea de Producción,» Redalyc, pp. 36-37, 2012. [29] P. S. Martín y R. E. Yepes, «Dimensionado óptimo de buffers con metodología kanban sin tarjetas,» de 3rd International Conference on Industrial Engineering and Industrial Management , Barcelona-Terrassa, 2009. [30] T. E. Vollman, C. Whybark, W. L. Berry y F. R. Jacobs, Planeacion y control de la producción. Administracion de la cadena de suministros, México: Mc Graw Hill, 2005. [31] J. A. Dominguez Machuca, S. Garcia Gonzales, A. Ruiz Jimenez, M. A. Dominguez Machuca y M. J. Alvarez Gil, Dirección de operaciones. Aspectos tácticos y operativos en la producción y los servicios, Madrid - España: Mc Graw Hill, 1995. [32] U. S. Karmarkar, «Capacity loading and release planning with work-in-progress (WIP) and leadtimes,» Journal of Manufacturing and Operations Management, vol. 2, nº 2, pp. 105-123, 1989. [33] T. Aouam, K. Kumar, K. Geryl y N. Brahimi, «Production planning with order acceptance and demand uncertainty,» Computers and Operations Research , vol. 91, p. 145–159, 2018. [34] A. Kefeli, R. Uzsoy, Y. Fathi y M. Kay, «Using a mathematical programming model to examine the marginal price of capacitated resources,» Int. J. Production Economics, vol. 131, p. 383–391, 2011. [35] S. N. Chapman, Planificación y control de la producción, México: Pearson Educación, 2006. [36] C. Belotti Pedroso, A. Lago da Silva y W. Lea tate, «Sales and Operations Planning (S&OP): Insights from a multi-case study of Brazilian Organizations,» International Journal of Production Economics, vol. 182, pp. 213-229, 2016. [37] Y. Nemati, M. Madhoshi y A. Safaei Ghadikolaei, «The effect of Sales and Operations Planning (S&OP) on supply chain’s total performance: A case study in an Iranian dairy company,» Computers & Chemical Engineering, vol. 104, pp. 323-338, 2017. [38] S. Wochner, M. Grunow, T. Staeblein y R. Stolletz, «Planning for ramp-ups and new product introductions in the automotive industry: Extending sales and operations planning,» International Journal of Production Economics, vol. 182, pp. 372-383, 2016. [39] S. Noroozi y J. Wikner, «Sales and operations planning in the process industry: A literature review,» International Journal of Production Economics, vol. 188, pp. 139-155, 2017. [40] C. T. Maravelias y C. Sung, «Integration of production planning and scheduling: Overview, challenges and opportunities,» Computers & Chemical Engineering, vol. 33, nº 12, pp. 1919-1930, 2009. [41] P. Jonsson y L. Kjellsdotter Ivert, «Improving performance with sophisticated master production scheduling,» International Journal of Production Economics, vol. 168, pp. 118-130, 2015. [42] H. Yochihiro Fuchigami y S. Rangel, «A survey of case studies in production scheduling: Analysis and perspectives,» Journal of Computational Science, vol. 25, pp. 425-436, 2018. [43] J. DELGADO y F. MARÍN, «Evolución en los sistemas de gestión empresarial. Del MRP al ERP,» Economía Industrial, vol. 331, pp. 51-58, 2000. [44] C. A. Garzón Gaitán, Sistemas integrados de información para la producción, Bogotá D.C: Universidad Nacional de Colombia , 2000. [45] G. Zäpfel, «Production planning in the case of uncertain individual demand Extension for an MRP II concept,» International Journal of Production Economics, vol. 46–47, pp. 153-164, 1996. [46] R. G. SCHROEDER, ADMINISTRACION DE OPERACIONES, México: MCGRAW-HILL, 1992. [47] G. Miño Cascante, E. S. Fonseca, A. Toledo Borrego , A. Roldan Ruenes y R. R. Moreno García, «Planeación de requerimientos de materiales por el sistema MRP. Caso Laboratorio Farmacéutico Oriente. Cuba,» Scielo, vol. 35, pp. 208-219, 2015. [48] O. B. Ammar, R. Guillaume y C. Thierry, «MRP parameter evaluation under fuzzy lead times,» IFAC-PapersOnLine, vol. Volume 49, nº 12, pp. 1110-1115, 2016. [49] Y. Ming, R. Houé y B. Grabot, «MRP-based negotiation in customer-supplier relationship,» IFAC Proceedings Volumes, vol. 45, nº 6, pp. 628-633, 2012. [50] C. X. Ayora, «PROPUESTA DE UN MODELO DE PROGRAMACION DE LA PRODUCCION PARA UNA EMPRESA METALMECÁNICA,» Repositorio tesis de grado Universidad Javeriana Cali , 2015. [51] C. Silva, V. Reis, A. Morais, I. Brilenkov, J. Vaza, T. Pinheiro, M. Neves, M. Henriques, M. L. Varela, G. Pereira, L. Dias, N. O. Fernandes y S. Carmo-Silva, «A comparison of production control systems in a flexible flow shop,» Procedia Manufacturing, vol. 13, pp. 1090-1095, 2017. [52] M. Niehues, G. Reinhart, T. Steinhaeusser y P. Sellmaier, «Adaptive Job-Shop Control Using Resource Accounts,» Procedia CIRP, vol. 57, pp. 351-356, 2016. [53] A. S. Xanthopoulos, D. E. Koulouriotis y A. Gasteratos, «Adaptive card-based production control policies,» Computers & Industrial Engineering, vol. 103, pp. 131-144, 2017. [54] Congreso de Colombia, «es.precidencia.gov.co,» 3 12 2017. [En línea]. Available: http://es.presidencia.gov.co/normativa/normativa/LEY%201846%20DEL%2018%20DE%20JULIO%20DE%202017.pdf. [55] R. Sampieri Hernandez, C. Fernandez Collado y M. d. p. Baptista Lucio, Metodología de la investigación, Mexico: Mc Graw Hill , 2010. [56] L. Blank y A. Tarquin, Ingeniería Económica, México D.F: McGraw-Hill, 2004. [57] R. Gomez Gutierrez y C. D. Sepulveda, «"Reducción de la variación de consumo de cobre y mano de obra en el proceso de barraje de una empresa fabricante de tableros eléctricos." Tesis de Pregrado,» Universidad de San Buenaventura, Cali, 2018. [58] J. K. Liker, The Toyota Way, New York : McGraw-Hill, 2004. |
dc.source.instname.spa.fl_str_mv |
Universidad de San Buenaventura - Cali |
dc.source.other.spa.fl_str_mv |
Cali, Trabajo de Grado, T658.515 R173p |
dc.source.reponame.spa.fl_str_mv |
Biblioteca Digital Universidad de San Buenaventura |
bitstream.url.fl_str_mv |
https://bibliotecadigital.usb.edu.co/bitstreams/b6a42460-da1f-426a-9873-475ef40f4837/download https://bibliotecadigital.usb.edu.co/bitstreams/9dbd80ae-49c8-4f5d-98c1-ad5b3250d62e/download https://bibliotecadigital.usb.edu.co/bitstreams/eca69bf7-dc48-4ade-a602-217977ccf9a5/download https://bibliotecadigital.usb.edu.co/bitstreams/f51283d5-8244-4fcd-bd47-d2da7b49df9e/download https://bibliotecadigital.usb.edu.co/bitstreams/233e9b3f-1a86-42bf-8464-affc6059e402/download |
bitstream.checksum.fl_str_mv |
faa66988b4f3a4299704416630f9631e 07e45e5e334f7f80c33c04712b25390c 0c7b7184e7583ec671a5d9e43f0939c0 93333d1c41582267a03e228aeff79798 e4666da2577ac6957c99a2810ac67644 |
bitstream.checksumAlgorithm.fl_str_mv |
MD5 MD5 MD5 MD5 MD5 |
repository.name.fl_str_mv |
Repositorio Institucional Universidad de San Buenaventura Colombia |
repository.mail.fl_str_mv |
bdigital@metabiblioteca.com |
_version_ |
1812932473948995584 |
spelling |
Comunidad Científica y AcadémicaAyora Piedrahita, Claudia Ximena9ecfbdcb-99b0-409d-877c-03ac6560942f-1Ramírez Jiménez, Carlos Alberto1f233ea8-31bf-4edd-a618-b6e7b79652d7-1Espinosa Valencia, Yerson Alberto5ca8bb4b-73f6-4d7b-8bfd-be846f580bd1-12019-02-22T15:44:52Z2019-02-22T15:44:52Z20192019-02-22This paper proposes to model of planning, programming and control production to one company that make products for the electric sector under a productive environment Job Shop - Make To Order, this company in the last year, in the months on August, September and October fail in fulfillment 70% of orders, with an average delay of 12 business days according to the delivery date agreed with the customers. An causes analysis is carried out and weaknesses have been identified in the planning, programming and control of operations in the production processes for current half and voltage transformers, a model is presented for the elaboration of a plan of production, a master production plan (MPS), material requirements plan (MRP) and a production program validated by means of a selection design for two sequencing rules based on the objectives set, using the scoring methodology is rated as performance indicator the Average Work Delay (RPT) , and the rule First in Arriving First in Service (PLLPS) is selected, finally it is validated in the implementation that the fulfillment of the orders improved by 43% and was reduced the average delay of works to 0 days.Este trabajo propone un modelo de planeación, programación y control de la producción para una empresa que fabrica productos para el sector eléctrico bajo un ambiente productivo Job Shop - Make To Order, la cual para Agosto, Septiembre y Octubre del año 2017 presentó un incumplimiento en el 70% de las órdenes de pedido, con una tardanza media de 12 días laborales de acuerdo a la fecha de entrega pactada con los clientes.Se realiza un análisis de causas y se identifica falencias en la planeación, programación y el control de las operaciones en los procesos de producción para transformadores de media corriente y media tensión, se presenta un modelo para la elaboración de un plan de producción, un plan maestro de producción (MPS), plan de requerimiento de materiales (MRP) y un programa de producción validado por medio de un diseño de selección para dos reglas de secuenciación en función de los objetivos planteados, por medio de la metodología Scoring se califica como indicador de rendimiento el Retraso promedio de trabajos (RPT), y se selecciona la regla Primero en Llegar Primero en Servir (PLLPS), finalmente se valida en la implementación que el cumplimiento de las ordenes mejoró en un 43% y se redujo el retraso promedio de trabajos a 0 días.pdf131 páginas: ilustracionesRecurso en lineaapplication/pdfhttp://hdl.handle.net/10819/6938spaUniversidad de San Buenaventura, CaliIngenieriasIngeniería IndustrialCaliAtribución-NoComercial-SinDerivadas 2.5 ColombiaPor medio de este formato manifiesto mi voluntad de AUTORIZAR a la Universidad de San Buenaventura, Sede Bogotá, Seccionales Medellín, Cali y Cartagena, la difusión en texto completo de manera gratuita y por tiempo indefinido en la Biblioteca Digital Universidad de San Buenaventura, el documento académico-investigativo objeto de la presente autorización, con fines estrictamente educativos, científicos y culturales, en los términos establecidos en la Ley 23 de 1982, Ley 44 de 1993, Decisión Andina 351 de 1993, Decreto 460 de 1995 y demás normas generales sobre derechos de autor. Como autor manifiesto que el presente documento académico-investigativo es original y se realiza sin violar o usurpar derechos de autor de terceros, por lo tanto, la obra es de mi exclusiva autora y poseo la titularidad sobre la misma. La Universidad de San Buenaventura no será responsable de ninguna utilización indebida del documento por parte de terceros y será exclusivamente mi responsabilidad atender personalmente cualquier reclamación que pueda presentarse a la Universidad. Autorizo a la Biblioteca Digital de la Universidad de San Buenaventura convertir el documento al formato que el repositorio lo requiera (impreso, digital, electrónico o cualquier otro conocido o por conocer) o con fines de preservación digital. Esta autorización no implica renuncia a la facultad que tengo de publicar posteriormente la obra, en forma total o parcial, por lo cual podrá, dando aviso por escrito con no menos de un mes de antelación, solicitar que el documento deje de estar disponible para el público en la Biblioteca Digital de la Universidad de San Buenaventura, así mismo, cuando se requiera por razones legales y/o reglas del editor de una revista.http://creativecommons.org/licenses/by-nc-nd/2.5/co/http://purl.org/coar/access_right/c_abf2[1] Comercio Exterior - DINERO, «DINERO,» 22 2 2018. [En línea]. Available: http://www.dinero.com/economia/articulo/28-anos-apertura-economica/255671. [Último acceso: 13 3 2018]. [2] Grupo de Investigación en nuevas tecnologias , «Modelo de Planeación - Documento en Curso,» Programa de Ing. Industrial, Cali , 2017. [3] F. Perzella, G. Morganti. y G. Ciaschetti, «A genetic algorithm for the Flexible Job-shop Scheduling Problem,» Computers & Operations Research, vol. 35, pp. 3202 - 3212, 2008. [4] RITZ, «RITZ Instrument Transformers,» 16 Noviembre 2017. [En línea]. Available: http://ritz-international.com/language/es/productos/1365-2/. [Último acceso: 26 01 2018]. [5] J. A. M. Idarraga, «Propuesta para implementar un sistemas de programacionde la produccion,bajo teoria de restricciones, en una empresa de artes graficas.,» Universidad de Antioquia, Medellin, 2006. [6] C. R. d. l. R. Navas, «Planeación y control del proceso de producción de vigueta y poste pretensado de la empresa precon,» Universidad de San Carlos de Guatemala, Guatemala, 2015. [7] A. V. Pereira, «Análisis y desarrollo del sistema de planeación y control de la producción en una empresa de confecciones,» Cali, 2013. [8] A. Hees, C. Bayerl, B. V. Vuuren, C. S. Schutte, S. Braunreuther y G. Reinhart, «A production planning method to optimally exploit the potential of reconfigurable manufacturing systems,» Procedia CIRP, pp. 181-185, 2017. [9] R. J. Sampaio, R. R.G.Wollmann y P. F.G.Vieira, «A flexible production planning for rolling-horizons,» Int. J. Production Economics, pp. 31-36, 2017. [10] S. H. Kim y Y. H. Lee, «Synchronized production planning and scheduling in semiconductor fabrication,» Computers & Industrial Engineering, pp. 72-84, 2016. [11] A. T. ,. V. V. Carlos Herrera, «Simulation of a Hybrid Product-Driven System for Manufacturing Planning and Control,» IFAC Proceedings Volumes, pp. 69-73, 2013. [12] K. Y.P.Martínez, E. A.V.Toso y ReinaldoMorabito, «Production planning in the molded pulp packaging industry,» Computers & Industrial Engineering, pp. 554-566, 2016. [13] L. Shen, S. Dauzere y J. S, «Solving the flexible job shop scheduling problem with sequence-dependent setup times,» European Journal of Operational Research, vol. 265, pp. 503 - 516, 2018. [14] N. Kundakcı y O. Kulak, «Hybrid genetic algorithms for minimizing makespan in dynamic job shop scheduling problem,» Computers & Industrial Engineering, vol. 96, pp. 31-51, 2016. [15] K. Zhou Gao, P. Nagaratnam Suganthan, T. Jin Chua y C. Soon Chong, «A two-stage artificial bee colony algorithm scheduling flexible job-shop scheduling problem with new job insertion,» Expert Systems with Applications, vol. 42, pp. 7652 - 7663, 2015. [16] Z. Z. Mengna Hong, Y. Man, J. L. Yanzhong Zhang y H. Liu, «Multi-object optimization of flexible flow shop scheduling with batch process — Consideration total electricity consumption and material wastage,» Journal of Cleaner Production, vol. 183, pp. 925 - 939, 2018. [17] B. Shi, X. Qian, S. Sun y L. Yan, «Rule-based scheduling of multi-stage multi-product batch plants with parallel units,» Chinese Journal of Chemical Engineering, vol. 25, pp. 1022 - 1036, 2017. [18] E. G. Birgina, J. E. Ferreirab y D. P. Ronconib, «List scheduling and beam search methods for the flexible job shop scheduling problem with sequencing flexibility,» European Journal of Operational Research, vol. 247, pp. 4021-4040, 2015. [19] U. Golle , N. Boysen y F. Rothlauf, «Analysis and design of sequencing rules for car sequencing,» European Journal of Operational Research , vol. 206, p. 579–585, 2010. [20] R. Romero Silva , S. Shaaban, E. Marsillac y M. Hurtado , «Exploiting the characteristics of serial queues to reduce the mean and variance of flow time using combined priority rules,» International Journal of Production Economics , vol. 196 , p. 211–225, 2018. [21] 16 Noviembre 2017. [En línea]. Available: https://atelelectric.com/aisladores/. [Último acceso: 26 01 2018]. [22] C. J. B. Pérez, Producción y operaciones aplicadas a las pyme, ECOE EDICIONES, 2015. [23] J. G. Babon y L. C. Arbos, Gestion integral de la calidad (5ta Edicion), Barcelona: PROFIT, 2017. [24] R. A. Rojas Medina, «Contabilidad de costos,» de Contabilidad de costos un enfoque administrativo y de Gerencia, Manizales, ( No publicado), 2014, pp. 1-8. [25] S. Song, KannanGovindan, L. Xu, P. Du y X. Qiao, «Capacity and production planning with carbon emission constraints,» Transportation Research Part E, pp. 1-2, 2017. [26] HuataoPeng y YangLiu, «A comprehensive analysis of cleaner production policies in China,» Journal of Cleaner Production, pp. 1-3, 2016. [27] Sin-HoonHum, MahmutParlar y YunZhou, «Measurement and optimization of responsiveness in supply chain networks with queueing structures,» European Journal of Operational Research, pp. 106-107, 2018. [28] M. P. M. Vázquez y M. J. M. Ruíz, «Elementos que Afectan el Nivel de Inventario en Proceso (WIP) y los Costos de una Línea de Producción,» Redalyc, pp. 36-37, 2012. [29] P. S. Martín y R. E. Yepes, «Dimensionado óptimo de buffers con metodología kanban sin tarjetas,» de 3rd International Conference on Industrial Engineering and Industrial Management , Barcelona-Terrassa, 2009. [30] T. E. Vollman, C. Whybark, W. L. Berry y F. R. Jacobs, Planeacion y control de la producción. Administracion de la cadena de suministros, México: Mc Graw Hill, 2005. [31] J. A. Dominguez Machuca, S. Garcia Gonzales, A. Ruiz Jimenez, M. A. Dominguez Machuca y M. J. Alvarez Gil, Dirección de operaciones. Aspectos tácticos y operativos en la producción y los servicios, Madrid - España: Mc Graw Hill, 1995. [32] U. S. Karmarkar, «Capacity loading and release planning with work-in-progress (WIP) and leadtimes,» Journal of Manufacturing and Operations Management, vol. 2, nº 2, pp. 105-123, 1989. [33] T. Aouam, K. Kumar, K. Geryl y N. Brahimi, «Production planning with order acceptance and demand uncertainty,» Computers and Operations Research , vol. 91, p. 145–159, 2018. [34] A. Kefeli, R. Uzsoy, Y. Fathi y M. Kay, «Using a mathematical programming model to examine the marginal price of capacitated resources,» Int. J. Production Economics, vol. 131, p. 383–391, 2011. [35] S. N. Chapman, Planificación y control de la producción, México: Pearson Educación, 2006. [36] C. Belotti Pedroso, A. Lago da Silva y W. Lea tate, «Sales and Operations Planning (S&OP): Insights from a multi-case study of Brazilian Organizations,» International Journal of Production Economics, vol. 182, pp. 213-229, 2016. [37] Y. Nemati, M. Madhoshi y A. Safaei Ghadikolaei, «The effect of Sales and Operations Planning (S&OP) on supply chain’s total performance: A case study in an Iranian dairy company,» Computers & Chemical Engineering, vol. 104, pp. 323-338, 2017. [38] S. Wochner, M. Grunow, T. Staeblein y R. Stolletz, «Planning for ramp-ups and new product introductions in the automotive industry: Extending sales and operations planning,» International Journal of Production Economics, vol. 182, pp. 372-383, 2016. [39] S. Noroozi y J. Wikner, «Sales and operations planning in the process industry: A literature review,» International Journal of Production Economics, vol. 188, pp. 139-155, 2017. [40] C. T. Maravelias y C. Sung, «Integration of production planning and scheduling: Overview, challenges and opportunities,» Computers & Chemical Engineering, vol. 33, nº 12, pp. 1919-1930, 2009. [41] P. Jonsson y L. Kjellsdotter Ivert, «Improving performance with sophisticated master production scheduling,» International Journal of Production Economics, vol. 168, pp. 118-130, 2015. [42] H. Yochihiro Fuchigami y S. Rangel, «A survey of case studies in production scheduling: Analysis and perspectives,» Journal of Computational Science, vol. 25, pp. 425-436, 2018. [43] J. DELGADO y F. MARÍN, «Evolución en los sistemas de gestión empresarial. Del MRP al ERP,» Economía Industrial, vol. 331, pp. 51-58, 2000. [44] C. A. Garzón Gaitán, Sistemas integrados de información para la producción, Bogotá D.C: Universidad Nacional de Colombia , 2000. [45] G. Zäpfel, «Production planning in the case of uncertain individual demand Extension for an MRP II concept,» International Journal of Production Economics, vol. 46–47, pp. 153-164, 1996. [46] R. G. SCHROEDER, ADMINISTRACION DE OPERACIONES, México: MCGRAW-HILL, 1992. [47] G. Miño Cascante, E. S. Fonseca, A. Toledo Borrego , A. Roldan Ruenes y R. R. Moreno García, «Planeación de requerimientos de materiales por el sistema MRP. Caso Laboratorio Farmacéutico Oriente. Cuba,» Scielo, vol. 35, pp. 208-219, 2015. [48] O. B. Ammar, R. Guillaume y C. Thierry, «MRP parameter evaluation under fuzzy lead times,» IFAC-PapersOnLine, vol. Volume 49, nº 12, pp. 1110-1115, 2016. [49] Y. Ming, R. Houé y B. Grabot, «MRP-based negotiation in customer-supplier relationship,» IFAC Proceedings Volumes, vol. 45, nº 6, pp. 628-633, 2012. [50] C. X. Ayora, «PROPUESTA DE UN MODELO DE PROGRAMACION DE LA PRODUCCION PARA UNA EMPRESA METALMECÁNICA,» Repositorio tesis de grado Universidad Javeriana Cali , 2015. [51] C. Silva, V. Reis, A. Morais, I. Brilenkov, J. Vaza, T. Pinheiro, M. Neves, M. Henriques, M. L. Varela, G. Pereira, L. Dias, N. O. Fernandes y S. Carmo-Silva, «A comparison of production control systems in a flexible flow shop,» Procedia Manufacturing, vol. 13, pp. 1090-1095, 2017. [52] M. Niehues, G. Reinhart, T. Steinhaeusser y P. Sellmaier, «Adaptive Job-Shop Control Using Resource Accounts,» Procedia CIRP, vol. 57, pp. 351-356, 2016. [53] A. S. Xanthopoulos, D. E. Koulouriotis y A. Gasteratos, «Adaptive card-based production control policies,» Computers & Industrial Engineering, vol. 103, pp. 131-144, 2017. [54] Congreso de Colombia, «es.precidencia.gov.co,» 3 12 2017. [En línea]. Available: http://es.presidencia.gov.co/normativa/normativa/LEY%201846%20DEL%2018%20DE%20JULIO%20DE%202017.pdf. [55] R. Sampieri Hernandez, C. Fernandez Collado y M. d. p. Baptista Lucio, Metodología de la investigación, Mexico: Mc Graw Hill , 2010. [56] L. Blank y A. Tarquin, Ingeniería Económica, México D.F: McGraw-Hill, 2004. [57] R. Gomez Gutierrez y C. D. Sepulveda, «"Reducción de la variación de consumo de cobre y mano de obra en el proceso de barraje de una empresa fabricante de tableros eléctricos." Tesis de Pregrado,» Universidad de San Buenaventura, Cali, 2018. [58] J. K. Liker, The Toyota Way, New York : McGraw-Hill, 2004.Universidad de San Buenaventura - CaliCali, Trabajo de Grado, T658.515 R173pBiblioteca Digital Universidad de San BuenaventuraPlaneación de la producciónPlan maestro de la producciónPlaneación de recursos de manufacturaPlaneación de ventas y operacionesProducción bajo pedidoJob shopSecuencia de operacionesControl de la producciónControl de plantaReglas de secuenciaciónPLLPSTPCProduction planningProduction master planPlanning of manufacturing resourcesSales planning and operationsOn-demand manufacturingWorkshopOrder fulfillmentOperations sequencingProduction controlSequencing rulesFIFOSPTMejoramiento de procesosPlaneación estratégicaControl de la producciónIngeniero IndustrialPropuesta e implementación de un modelo de planeación, programación y control de la producción en una empresa fabricante de productos para el sector eléctricoTrabajo de grado - PregradoTrabajo de Gradoinfo:eu-repo/semantics/bachelorThesishttp://purl.org/coar/resource_type/c_7a1fPublicationORIGINALPropuesta_Implementacion_Planeacion_Ramirez_2018.pdfPropuesta_Implementacion_Planeacion_Ramirez_2018.pdfapplication/pdf4698240https://bibliotecadigital.usb.edu.co/bitstreams/b6a42460-da1f-426a-9873-475ef40f4837/downloadfaa66988b4f3a4299704416630f9631eMD51Anexos_Propuesta_Implementacion_Planeacion_Ramirez.rarAnexos_Propuesta_Implementacion_Planeacion_Ramirez.rarapplication/octet-stream2803620https://bibliotecadigital.usb.edu.co/bitstreams/9dbd80ae-49c8-4f5d-98c1-ad5b3250d62e/download07e45e5e334f7f80c33c04712b25390cMD52LICENSElicense.txtlicense.txttext/plain; charset=utf-82071https://bibliotecadigital.usb.edu.co/bitstreams/eca69bf7-dc48-4ade-a602-217977ccf9a5/download0c7b7184e7583ec671a5d9e43f0939c0MD53TEXTPropuesta_Implementacion_Planeacion_Ramirez_2018.pdf.txtPropuesta_Implementacion_Planeacion_Ramirez_2018.pdf.txtExtracted texttext/plain270350https://bibliotecadigital.usb.edu.co/bitstreams/f51283d5-8244-4fcd-bd47-d2da7b49df9e/download93333d1c41582267a03e228aeff79798MD54THUMBNAILPropuesta_Implementacion_Planeacion_Ramirez_2018.pdf.jpgPropuesta_Implementacion_Planeacion_Ramirez_2018.pdf.jpgGenerated Thumbnailimage/jpeg7826https://bibliotecadigital.usb.edu.co/bitstreams/233e9b3f-1a86-42bf-8464-affc6059e402/downloade4666da2577ac6957c99a2810ac67644MD5510819/6938oai:bibliotecadigital.usb.edu.co:10819/69382023-02-23 16:24:38.2http://creativecommons.org/licenses/by-nc-nd/2.5/co/https://bibliotecadigital.usb.edu.coRepositorio Institucional Universidad de San Buenaventura Colombiabdigital@metabiblioteca.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 |